INSTALLATION GUIDE FOR RX-4122 
 
ENU STATUS : 1-0-1 
Copyright - refer to title page 
Page 23 
 
 
 
 
4  COMMISSIONING  
4.1 
PRE-COMMISSIONING TASKS 
After equipment installation, perform the following steps before equipment powering and commissioning: 
 
 
Verify that the expected voltage, current and power levels do not violate any ratings.  
 
Visually inspect the power connection within the equipment. Ensure that the power cable is correctly and 
securely connected, including the grounding wire, RF cable and other cables.  
 
Check the grounding connection and verify that the ground resistance is less than 5
Ω. 
 
Test  the  antenna  system  and  ensure  that  the  echo  loss  within  working  frequency  is  less  than  -14dB 
(VSWR<1.5).