4  COMMISSIONING 
4.1  PRE-COMMISSIONING TASKS 
After equipment installation, perform the following steps before equipment powering and commissioning, 
check that the expected voltage, current, and power levels do not violate any ratings. Double check all 
connections including ground before applying power. Do not manipulate circuits or make changes when 
power is applied: 
 
 
Visually inspect the power connection within the equipment. Ensure that all cables are correctly and 
securely connected, including power cables, grounding wires and RF cables.  
 
Check grounding connection and verify that 
the ground resistance is less than 5Ω.
 
 
Connect the equipment to the PC.  
 
Power on equipment. 
 
Monitor the initialization of the equipment though the LEDs on the panel. Refer to detailed LEDs 
information in the next section. 
 
 
4.2   LED INDICATORS 
Diagnostic LEDs are located on the equipment front panel; each indicates the status of a particular 
function: 
 
Table 5: LED Indications 
LED Indicator 
Normal Status 
Indication 
PWR 
Steady green 
Power indicator. If LED is off, it indicates the 
system has no power.  
RUN 
Flashing green 
(1 time/sec) 
mBDA operation indicator. After initialization 
(1~2 minutes), the LED should flash at once per 
sec. (When upgrade firmware, LED will flash 
rapidly)  
ALM 
OFF 
Alarm indicator. If LED is RED, there is an 
alarm.