Site requirements  6 
Site requirements 
HP Site Preparation Drawing Package 
HP provides detailed schematic engineer drawings of the HP POD 240a in the HP Site Preparation Drawing 
Package
, included on the documentation CD. 
 
Site preparation 
  
 
NOTE:
  The weight provided is an estimate. The total weight of the HP POD 240a will differ 
based on the IT equipment installed. 
  
The structural design of the HP POD 240a site pad design is based on specific weight load locations, 
accounting for the HP POD 240a structural footing and supported IT infrastructure. 
The HP POD 240a must be installed on a surface capable of supporting the following weights: 
 
HP POD 240a with 24 HVAC/DX units—117,526 kg (259,100 lb) 
 
HP POD 240a with 24 HVAC/DX units and IT equipment installed—Approximately 183,750 kg 
(405,100 lb) 
The site pad must be level with less than +/-0.5 degrees differential from extreme to extreme. Shimming is 
allowed when shims are used directly under the HP POD 240a load pads, and are placed in increments 
across the length of the HP POD 240a, ensuring the HP POD 240a is level. 
The customer is responsible for adequately protecting the surrounding environment during excavation. 
  
 
IMPORTANT:
  The HP POD 240a is designed for ground level installation. If you install the HP 
POD 240a on an elevated surface, make sure the minimum height requirements for circuit 
breaker actuators are considered per local and national electric code requirements. The area in 
front of the outside panels must include a work platform. 
  
For HP POD 240a load specifications and load distribution, see the HP Site Preparation Drawing Package 
(on page 
6
): 
 
External top view—Load distribution within IT sections 
 
External bottom view—Load bearing footprint 
 
External bottom view—Load bearing footprint, weights 
 
External bottom view—Load distribution pads (site dependant) 
 
Early infrastructure requirements 
The following work is expected to be complete on-site prior to the HP POD 240a assembly: 
 
Customer power equipment and feeders 
 
Underground construction requirements