LIQUID LEVEL CONTROL SYSTEM
Location:
 
The liquid level control system is composed of the 
circuit board in the right front corner of the hood and 
the probe in the tank lid.
Test Procedure:
1.   Disconnect  the  brewer  from  the  power  source 
and remove the wires from terminals 1 & 4 of the 
circuit board.
2.  With a voltmeter, check the voltage across termi-
nals 2 & 3 when the On/Left switch is in the upper 
position. Connect the brewer to the power source. 
The indication must be 120 volts ac.
3.  Disconnect the brewer from the power source.
If voltage is present as described, proceed to #4.
If voltage is not present as described, refer to the Wir-
ing Diagram  and check the brewer wiring harness.
4.  Reconnect the brown/white wire to terminal 1.
5.  Carefully connect a piece of insulated jumper wire 
to terminal 4. Keep the other end of this wire away 
FIG. 12 LIQUID LEVEL PROBE & CONTROL BOARD
PN
: 65
8
BUNN
OFF
HI
P2173.80
10179 121704
SERVICE (cont.)
from any metal surface of the brewer.
6.  With a voltmeter, check the voltage across termi-
nals 1 & 3 when the On/Left switch is in the upper 
position. Connect the brewer to the power source. 
The indication must be 120 volts ac after a delay 
of approximately 5 seconds.
7.  Touch the end of the jumper wire to the brewer 
housing. The indication must be zero.
8.  Move the jumper wire away from the brewer hous-
ing. The indication must again be 120 volts ac after 
a delay of approximately 5 seconds.
9.  Disconnect the brewer from the power source and 
remove the jumper wire from terminal 4.
If voltage is present as described, the liquid level con-
trol board is operating properly, proceed to #10.
If voltage is not present as described, replace the liquid 
level control board.
10. Reconnect the pink wire to terminal 4.
11. Gently pull the probe out of the tank lid and inspect 
for corrosion. Replace it if necessary.
12. Place the probe so that neither end is in contact 
with any metal surface of the brewer.
13. With a voltmeter, check the voltage across termi-
nals 1 & 3 when the On/Left switch is in the upper 
position. Connect the brewer to the power source. 
The indication must be 120 volts ac after a delay 
of approximately 5 seconds.
14. Touch the probe’s flat end to the brewer housing. 
The indication must be zero.
15. Move the probe’s flat end away from the brewer 
housing. The indication should again be 120 volts 
ac after a delay of approximately 5 seconds.
16. Disconnect the brewer from the power source.
If voltage is present as described, reinstall the probe, 
the liquid level control system is operating properly.
If voltage is not present as described, check the pink 
probe wire and/or replace the probe.