III.  Gas Control System Assembly  (Knockdown Boilers)
A.
  24V Standing Pilot Control System
 
Install Gas Control System.  All components are 
located in Combination Boiler Parts and Control 
Carton.
1.  Install Gas Control Assembly on Manifold.  See 
Figure 10. Use thread (joint) compound (pipe dope) 
resistant to action of liquefied petroleum gas.
2.  Install pilot burner piping and controls.  See Figure 
10.
3.  Connect Thermocouple Lead to Gas Valve.
4.  Mount Transformer (continuous circulation) or 
Control Center (intermittent circulation) to Junction 
Box.
a.  Canada only - loop 4” nylon cable tie between 
junction box and transformer/control center.
b.  Attach transformer/control center to junction 
box.
B.
  EI (Intermittent Ignition) 
 
Install Gas Control System.  All components are 
located in Combination Boiler Parts and Control 
Carton.
1.  Install Gas Control Assembly on Manifold.  See 
Figure 11. Use thread (joint) compound (pipe dope) 
resistant to action of liquefied petroleum gas.
2.  Install pilot burner piping and controls.
a.  Honeywell EI
i.  USA - See Figure 12.
ii.  Canada - See Figure 13.
3.  Install Ignition Module.
a.  Attach Ignition Control Mounting Bracket to 
Jacket Vestibule Panel using two (2) #8 x ½” 
sheet metal screws.
b.  Attach Honeywell Ignition Module to Mounting 
Bracket using two (2) #8 x ½” sheet metal 
screws.
c.  Connect pilot ground wire and ignitor/sensor 
lead(s) to ignition module. Refer to “Section VII:  
Electrical” for connection details.
4.  Mount Transformer (continuous circulation) or 
Control Center (intermittent circulation) to Junction 
Box.  See Figure 8.
a.  Canada only - loop 4” nylon cable tie between 
junction box and transformer/control center.
b.  Attach transformer/control center to junction 
box.
C.
  EP Control System
 
Install Gas Control System.  All components are 
located in Combination Boiler Parts and Control 
Carton.
1.  Install Gas Control Assembly on Manifold.  See 
Figure 14.
2.  Install pilot burner piping and controls.  See Figure 
14.
3.  Install Ignition Transformer.
a.  Attach Ignition Transformer to Jacket Vestibule 
Panel using four (4) #8 x ½” lg. sheet metal 
screws.
b.  Connect Ignition Lead from Pilot to Ignition 
Transformer.
4.  Mount Transformer (continuous circulation) or 
Control Center (intermittent circulation) to Junction 
Box.
a.  Canada only - loop 4” nylon cable tie between 
junction box and transformer/control center.
b.  Attach transformer/control center to junction 
box.
D.
  EP-CSD-1 Control System
 
Install Gas Control System.  All components are 
located in Combination Boiler Parts and Control 
Carton.
1.  Install Gas Control Assembly on Manifold.  See 
Figure 15.
2.  Install pilot burner piping and controls.  See Figure 
15.
3.  Install Ignition Transformer.
a.  Attach Ignition Transformer to Jacket Vestibule 
Panel using four (4) #8 x ½” lg. sheet metal 
screws.
b.  Connect Ignition Lead from Pilot to Ignition 
Transformer.
4.  Mount Transformer (continuous circulation) or 
Control Center (intermittent circulation) to Junction 
Box.
a.  Canada only - loop 4” nylon cable tie between 
junction box and transformer/control center.
b.  Attach transformer/control center to junction 
box.