Burnham Series 8H/8HE Boiler Manual De Propietario

Descargar
Página de 72
31
3.1    Breeching ducts are generally less flexible in design 
location than are water pipes.  To avoid conflicts for a 
given location, design and layout the breeching ducts 
before proceeding with water piping in this section.
3.1.1 The purpose of the Section 3.0 is to recommend 
piping systems and accessories that can be used with 
Series 8H/8HE Modular Gas Boilers.  Although 
recommended design procedures are presented, the 
final sizing of mains, pumps and compression tank 
must be left to the designer of the total system because 
only that designer has available the requirements and 
capacities of the connected system.
3.1.2  Please consider the serviceman who must periodically 
clean and adjust the boilers and repair accessories.  
Do not block passageways with piping.  Do not block 
access panels on the boiler jackets.
3.2    MANIFOLDS—Selection of the proper manifolds is 
important to the success of the modular concept.  One 
of the prime reasons for using modular boilers instead 
of a single large boiler is to improve the seasonal fuel 
efficiency.  Boiler losses are highest when the burner 
is off and the boiler is still warm.  Thus, if one small 
module can carry the heating load during mild outdoor 
weather by nearly continuous firing, a significant loss 
can be prevented and greater utilization of fuel can 
be made.  However, poor selection of manifolding 
can wipe out part or all of the potential fuel savings 
of the modular system.  Some provision should be 
made to prevent water from flowing through any 
module when it is not being fired.  When warm 
system water is allowed to flow through any unfired 
module, heat is being wasted by convection through 
the chimney and jacket of that unfired module.  For 
example, on an eight module system fired by an eight 
step sequencer, only one module may be required 
to meet the connected load demand on a day that 
is 55°F outdoors.  That would be a highly efficient 
operation.  However, if the system water is allowed 
to flow through the other seven modules, they too are 
kept warm and the total jacket and flue losses of the 
eight modules may be as great as that of a single large 
boiler.  Thus, intended benefit is lost.
3.2.1  Figure 3-1 shows a typical parallel pumping system.  
Parallel pumping of modules does not prevent flow 
through unfired modules as commonly installed.  
Thus, parallel pumping is not desirable unless a 
motorized valve is used on the supply pipe from each 
module and controlled to open only when that module 
is fired.  With motorized valves, the owner may find 
objectionable noise from high velocity water flow 
under light loads when the entire flow of the system 
pump is directed through only one module of the 
group.
3.2.2  By contrast, primary-secondary pumping provides 
positive flow through each module only when that 
module is fired.  Figure 3-2 shows such a system.  
The piping is simple and uses only a single header 
made up of fabricated steel manifolds available as 
optional equipment.  By keeping the head above 
the top of the modules as shown in Figure 3-2, any 
gravity circulation from header to unfired modules 
is prevented.  Flow through each fired module is 
balanced as a result of having its own secondary 
circulator.
sEcTION 3.0 wATER PIPING
burnham commercial recommends maintaining temperature differential (drop) across the system at 
40°f or less and return water temperature at minimum of 135°f.
cONTINUED bOILER OPERATION fOR PROLONGED PERIODs Of TIME UNDER cONDITIONs whEN 
TEMPERATURE DIffERENTIAL AcROss ThE sysTEM ExcEEDs 40°f AND/OR RETURN wATER 
TEMPERATURE sTAys bELOw 135°f, MAy REsULT IN PREMATURE bOILER fAILURE DUE TO fLUE 
GAs cONDENsATION AND/OR ThERMAL shOck.
If ThE AbOVE cONDITIONs ExIsT, TO PROTEcT A bOILER fROM sUsTAINED fLUE GAs cONDENsATION 
AND/OR ThERMAL shOck, ThE AbOVE-REcOMMENDED TEMPERATUREs MAy bE MAINTAINED by 
EMPLOyING cOMMON INDUsTRy-AccEPTED MIxING METhODs TO PROVIDE bOILER PROTEcTION.
some common methods are boiler by-pass piping, blend pumps, primary secondary piping with a by-
pass, mixing valves and/or variable speed injection pumps.
Recommended Water Quality Requirements
ph:  8.3 - 10.5
TDs:  < 3500 ppm
Total alkalinity ppm as cacO
:  < 1200
Total copper ppm:  < .05
Oily matter ppm:  < -1
Total harness ppm:  < -3
chlorides:  < 50 ppm
Pressure relief valve discharge piping must be 
piped such that the potential of severe burns 
is eliminated.  DO NOT pipe in any area where 
freezing could occur.  DO NOT install any shut off 
valves, plugs or caps.  consult Local codes for 
proper discharge piping arrangement.