Burnham Series 8H/8HE Boiler Manual De Propietario
31
3.1 Breeching ducts are generally less flexible in design
location than are water pipes. To avoid conflicts for a
given location, design and layout the breeching ducts
before proceeding with water piping in this section.
3.1.1 The purpose of the Section 3.0 is to recommend
piping systems and accessories that can be used with
Series 8H/8HE Modular Gas Boilers. Although
recommended design procedures are presented, the
final sizing of mains, pumps and compression tank
must be left to the designer of the total system because
only that designer has available the requirements and
capacities of the connected system.
3.1.2 Please consider the serviceman who must periodically
clean and adjust the boilers and repair accessories.
Do not block passageways with piping. Do not block
access panels on the boiler jackets.
3.2 MANIFOLDS—Selection of the proper manifolds is
important to the success of the modular concept. One
of the prime reasons for using modular boilers instead
of a single large boiler is to improve the seasonal fuel
efficiency. Boiler losses are highest when the burner
is off and the boiler is still warm. Thus, if one small
module can carry the heating load during mild outdoor
weather by nearly continuous firing, a significant loss
can be prevented and greater utilization of fuel can
be made. However, poor selection of manifolding
can wipe out part or all of the potential fuel savings
of the modular system. Some provision should be
made to prevent water from flowing through any
module when it is not being fired. When warm
system water is allowed to flow through any unfired
module, heat is being wasted by convection through
the chimney and jacket of that unfired module. For
example, on an eight module system fired by an eight
step sequencer, only one module may be required
to meet the connected load demand on a day that
is 55°F outdoors. That would be a highly efficient
operation. However, if the system water is allowed
to flow through the other seven modules, they too are
kept warm and the total jacket and flue losses of the
eight modules may be as great as that of a single large
boiler. Thus, intended benefit is lost.
3.2.1 Figure 3-1 shows a typical parallel pumping system.
Parallel pumping of modules does not prevent flow
through unfired modules as commonly installed.
Thus, parallel pumping is not desirable unless a
motorized valve is used on the supply pipe from each
module and controlled to open only when that module
is fired. With motorized valves, the owner may find
objectionable noise from high velocity water flow
under light loads when the entire flow of the system
pump is directed through only one module of the
group.
3.2.2 By contrast, primary-secondary pumping provides
positive flow through each module only when that
module is fired. Figure 3-2 shows such a system.
The piping is simple and uses only a single header
made up of fabricated steel manifolds available as
optional equipment. By keeping the head above
the top of the modules as shown in Figure 3-2, any
gravity circulation from header to unfired modules
is prevented. Flow through each fired module is
balanced as a result of having its own secondary
circulator.
sEcTION 3.0 wATER PIPING
burnham commercial recommends maintaining temperature differential (drop) across the system at
40°f or less and return water temperature at minimum of 135°f.
cONTINUED bOILER OPERATION fOR PROLONGED PERIODs Of TIME UNDER cONDITIONs whEN
cONTINUED bOILER OPERATION fOR PROLONGED PERIODs Of TIME UNDER cONDITIONs whEN
TEMPERATURE DIffERENTIAL AcROss ThE sysTEM ExcEEDs 40°f AND/OR RETURN wATER
TEMPERATURE sTAys bELOw 135°f, MAy REsULT IN PREMATURE bOILER fAILURE DUE TO fLUE
GAs cONDENsATION AND/OR ThERMAL shOck.
If ThE AbOVE cONDITIONs ExIsT, TO PROTEcT A bOILER fROM sUsTAINED fLUE GAs cONDENsATION
If ThE AbOVE cONDITIONs ExIsT, TO PROTEcT A bOILER fROM sUsTAINED fLUE GAs cONDENsATION
AND/OR ThERMAL shOck, ThE AbOVE-REcOMMENDED TEMPERATUREs MAy bE MAINTAINED by
EMPLOyING cOMMON INDUsTRy-AccEPTED MIxING METhODs TO PROVIDE bOILER PROTEcTION.
some common methods are boiler by-pass piping, blend pumps, primary secondary piping with a by-
some common methods are boiler by-pass piping, blend pumps, primary secondary piping with a by-
pass, mixing valves and/or variable speed injection pumps.
Recommended Water Quality Requirements
ph: 8.3 - 10.5
TDs: < 3500 ppm
Total alkalinity ppm as cacO
TDs: < 3500 ppm
Total alkalinity ppm as cacO
3
: < 1200
Total copper ppm: < .05
Oily matter ppm: < -1
Total harness ppm: < -3
chlorides: < 50 ppm
Oily matter ppm: < -1
Total harness ppm: < -3
chlorides: < 50 ppm
Pressure relief valve discharge piping must be
piped such that the potential of severe burns
is eliminated. DO NOT pipe in any area where
freezing could occur. DO NOT install any shut off
valves, plugs or caps. consult Local codes for
proper discharge piping arrangement.