D. Turn boiler on and verify that fuel valves are 
closed during the burner pre-purge cycle. Turn 
boiler off and disconnect power.
E. Adjust burner according to the burner 
manufacturer's specifications.  Target CO
2
 level is  
13% for optimum efficiency, but a range of 12.5 -   
13.0% is acceptable.
4.  TEST CONTROLS
Before installation of the boiler is considered 
complete the operation of the boiler controls 
should be checked, particularly the low water 
cutoff and the high limit control.
A. Check Operating Control  Raise and lower  
 
operating control setting as required to start and    
stop burner.
B. Warning  Check High Limit Control  
   Jumper Operating Control Terminals. Allow 
Burner to operate until shut down by limit. 
Installation is not considered complete until this 
check has been made. REMOVE JUMPER.
C. Check Low Water Cut-Off  control with water 
level at normal waterline. Raise operating control   
setting to allow burner to operate. Open boiler    
drain to allow water level to drop until burner  
 
operation is shut down by low water cutoff. 
DO NOT ALLOW THE BOILER TO OPERATE BELOW 
THE MINIMUM PERMISSIBLE WATER LEvEL AS 
INDICATED ON THE BOILER.
 
Close boiler drain and refill to normal water line. 
Unless boiler is equipped with a manual reset low water 
cutoff, burner should automatically restart during fill. 
Reset operating control.
PROBE AND FLOAT TYPE LOW WATER CUT-OFF 
DEvICES REQUIRE ANNUAL INSPECTION AND 
MAINTENANCE. Refer to Service Instructions, 
Section Iv for proper cleaning instructions.
D. Check Operating Control  on boiler equipped 
with a tankless heater. With burner off, draw hot 
water until burner starts, then turn off hot water 
and check burner shut down.
1.  Always inspect installation before starting 
burner.
2.  Fill heating system with water.
  
Any time that raw water is introduced to the boiler 
it must be heated to at least 180ºF immediately to 
dissipate the dissolved gases which can otherwise 
cause internal corrosion to the boiler.
A. Steam Boilers  Fill boiler to normal water line.  
 
Water should be visible in the gauge glass.  
 
After boiler is in operation, make up water should 
be added slowly to maintain the water level. 
B.  Hot Water Boilers  In a hot water heating system, 
the boiler and the entire system (other than 
the tank) must be full of water for satisfactory 
operation. Water  should be added to the system 
until the boiler pressure    
 
 
gauge registers normal system design operating  
pressure. To ensure that the system is full, water 
should come out of all air vents when opened.
ON A HOT WATER SYSTEM THE PRESSURE MUST 
NOT EXCEED 30 POUNDS UNLESS THE BOILER IS 
ESPECIALLY DESIGNED FOR A HIGHER MAXIMUM 
WORKING PRESSURE. IF A BOILER PRESSURE 
EXCEEDS PRESSURE SETTING OF SAFETY RELIEF 
vALvE, vALvE WILL RELIEvE IMMEDIATELY, BUT 
CAUSE OF RELIEF MUST BE INvESTIGATED AND 
CORRECTED. EXCESS PRESSURE IS DANGEROUS, 
IN ADDITION, COULD CAUSE DAMAGE TO HEATING 
SYSTEM, PERSONAL INJURY OR SERIOUS 
PROPERTY DAMAGE.
DO NOT draw water from the boiler while in use. 
When adding water while boiler is in operation, 
do not open the supply valve fully, but add water 
slowly.
 
3. BURNER
A. Check wiring of all fuel valves. Verify that wiring 
is correct according to the factory supplied wiring 
diagram.
B. Leave all manual fuel valves closed. This includes  
manual shutoff valves supplied with the boiler and 
facility installed valves at the boiler site.
C. Perform all burner pre-startup checks according 
to the burner manufacturer's specifications. Refer 
to the burner manufacturer's installation manual    
furnished with the boiler.
SECTION III  — OPERATING INSTRUCTIONS