Section 1.  Preparation and Siting
These guidelines apply to several different Campbell Scientific weather stations.
1.1  Installation Tasks
1.1.1  Indoors
 
Immediately upon receipt of your shipment…
⇒  Open shipping cartons.
⇒  Check contents against invoice.  Contact CSI immediately about any
shortages.
 
Several days prior to the planned installation date…
⇒  Collect tools and site information (Section 1)
⇒  Assemble datalogger, communications device, and power supply in
enclosure (Section 3)
⇒  Install datalogger support software on PC (Section 5)
⇒  Establish communications between the datalogger and the PC
(Section 5)
⇒  Program datalogger, test sensors, and retrieve data (Section 5)
⇒  Trial run the tower / tripod installation, assembling as much as
possible (Section 2)
⇒  Repackage equipment for transport to the field site
1.1.2  Outdoors
 
Locate suitable site (Section 1)
 
Prepare tower or tripod base (Section 2)
 
Tripod and UT10 (3 meter tower) tower stations:
⇒  Raise tripod or tower (Section 2)
⇒  Install instrumentation enclosure (Section 3)
⇒  Install sensors (Section 4)