Schneider Electric PM5300 Manual De Usuario

Descargar
Página de 120
PowerLogic™ PM5300 series user guide 
Chapter 3—Hardware Reference
© 2014 Schneider Electric All Rights Reserved
25
Voltage and current input wiring
For wiring instructions and safety precautions, see the meter installation sheet that was 
shipped with your meter, or download a copy at www.schneider-electric.com.
Voltage input protection
The meter’s voltage inputs must be wired to fuses/breakers and a disconnect switch. If 
using a voltage transformer (VT), both primary and secondary sides of the VT must be 
wired to fuses/breakers and disconnect switches.
Clearly label the device’s disconnect circuit mechanism and install it within easy reach 
of the operator.
The fuses / circuit breakers must be rated for the installation voltage and sized for the 
available fault current.
Fuse for neutral terminal is required if the source neutral connection is not grounded.
See the meter installation sheet for fuse ratings.
Current input protection
For all connected current inputs, use a CT shorting block to short-circuit the secondary 
leads of the CTs before removing the current input connections to the meter.
NOTE:
Ground any unused current inputs.
3-phase 4-wire Delta center-tapped

3PH4W Dlt Ctr Tp
240 V L-N / 
415 V L-N / 
480 V L-L
240 V L-N / 
415 V L-N / 
480 V L-L
3 VT
3-phase 4-wire ungrounded Wye

3PH4W Wye Ungnd
347 V L-N / 
600 V L-L
347 V L-N / 
600 V L-L
3 VT or 2 VT
3-phase 4-wire grounded Wye

3PH4W Wye Gnd
347 V L-N / 
600 V L-L
400 V L-N / 
690 V L-L
3 VT or 2 VT
3-phase 4-wire resistance-grounded 
Wye

3PH4W Wye Res Gnd
347 V L-N / 
600 V L-L
347 V L-N / 
600 V L-L
3 VT or 2 VT
Power system setup parameters (continued)
Power system description

Meter setting
Symbol
Direct connect maximum
# of VTs
(if required)
UL
IEC
N
N
N