Guardian Technologies 4582 & 4987 Manual De Usuario

Descargar
Página de 90
section 6
Diagnostic tests
Page 41
TERMINAL 
BLOCK 
(TB1)
12.00
86
15B
167
BLK
0
229
83
BLK
TR2
TR1
Figure 6-5. – Testing Wire 15B
TB1
J2 HARNESS CONNECTOR
00.00
86
15B
167
BLK
0
229
83
BLK
TR2
TR1
J2-1
J2-12
MAKE SURE THE TEST 
PROBE CONNECTOR IS 
MAKING CONTACT 
WITH THE CONNECTOR. 
DOUBLE CHECK TO 
MAKE SURE THAT THE 
TIP IS SHARP.
Figure 6-6. – Testing J2-1
RESULTS:
1. If the stepper motor fails any part of Step 5 replace the stepper
motor.
2. If  Step  7  fails  repair  or  replace Wire  15B  between  the  Start-
Run-Stop Relay (SSR) and Terminal Block TB1.
3. If the stepper motor passes all steps replace the Printed Circuit
Board.
TEST 6 - WIRE CONTINUITY
PROCEDURE:
1. Set a Voltmeter to measure resistance.
2. Remove the six pin connector from the Voltage Regulator.
3. Connect one meter test lead to Wire 0 in the six pin connector
previously removed from the Voltage Regulator. See Figure 6-
11. Be careful not to damage the pin connectors with the test
leads.
3. Connect the other test lead to the ground terminal in the control
panel. The meter should read continuity.
4. Connect one meter test lead to Wire 162 in the six pin connec-
tor previously removed from the Voltage Regulator. See Figure
6-11. Be careful not to damage the pin connectors with the test
leads.
5. Remove Wire  162  from  the  Excitation  Circuit  Breaker  (CB1).
Connect  the  other  meter  test  lead  to Wire  162. The  meter
should read continuity.
RESULTS:
If  continuity  was  NOT  measured  across  each  wire, 
repair  or  replace  the  wires  as  needed.  If  continuity 
WAS measured refer back to flow chart.
TEST 7 - CHECk FIELd bOOST
PROCEDURE:
1. Set VOM to measure DC voltage.
2. Disconnect the six pin connector from the Voltage Regulator.
3. Disconnect Connector C1. See Page 17 for connector location.
4. Disconnect Wire  16  from  the  Starter  Contactor  Relay  (SCR).
See  Figure  6-13. This  will  cause  the  unit  not  to  crank  when
placed in the Start position.
5. Connect  the  positive  meter  test  lead  to Wire  4  at  the  diode
(D1), Wire 4 is soldered to the diode. See Figure 6-14. Connect
the negative meter test lead to the ground terminal.
6. Set the Start-Run-Stop Switch (SW1) to START. Measure the
DC voltage. It should read approximately 12 VDC.
7. Reconnect  the  Six  Pin  connector  to  the Voltage  Regulator,
Reconnect  the  C1  connector,  and  reconnect Wire  16  to  the
Starter Contactor Relay.
RESULTS:
1. If  12 VDC  was  measured  in  Step  5  the  field  boost  circuit  is
working refer back to the flow chart.
2. If field boost voltage was not measured refer back to the flow
chart.