12. Connect the meter test leads across Stator lead 2 (Pin 6) at
the C1 connector female side and frame ground. Be careful not
to  damage  the  pin  connectors  with  the  test  leads,  use  paper
clips - do not force probes into connectors. See Figure 6-18.
INFINITY should be read.
13. Connect the meter test leads across Stator lead 66 (Pin 9) at
the C1 connector female side and frame ground. Be careful not
to  damage  the  pin  connectors  with  the  test  leads,  use  paper
clips - do not force probes into connectors. See Figure 6-18.
INFINITY should be read.
14. Connect the meter test leads across Stator leads Wire 11 and
Stator  lead  66A  (Pin  4)  at  the  C1  connector  female  side.  Be
careful not to damage the pin connectors with the test leads,
use  paper  clips  -  do  not  force  probes  into  connectors.    See
Figure 6-18. INFINITY should be read.
15. Connect the meter test leads across Stator leads Wire 11 and
Stator lead 2 (Pin 6) at the C1 connector female side. Be care-
ful not to damage the pin connectors with the test leads, use
paper clips - do not force probes into connectors. See Figure
6-18. INFINITY should be read.
16. Connect the meter test leads across Stator leads Wire 11 and
Stator lead 66 (Pin 9) at the C1 connector female side. Be care-
ful not to damage the pin connectors with the test leads, use
paper clips - do not force probes into connectors. See Figure
6-18. INFINITY should be read.
17. Connect the meter test leads across Stator lead 66A (Pin 4)
and Stator lead 2 (Pin 6) at the C1 connector female side. Be
careful not to damage the pin connectors with the test leads,
use  paper  clips  -  do  not  force  probes  into  connectors.    See
Figure 6-18. INFINITY should be read.
18. Connect the meter test leads across Stator lead 66A (Pin 4)
and Stator lead 66 (Pin 9) at the C1 connector female side. Be
careful not to damage the pin connectors with the test leads,
use  paper  clips  -  do  not  force  probes  into  connectors.    See
Figure 6-18. INFINITY should be read.
19. Connect the meter test leads across Stator lead 2 (Pin 6) and
Stator lead 66 (Pin 9) at the C1 connector female side. Be care-
ful not to damage the pin connectors with the test leads, use
paper clips - do not force probes into connectors. See Figure
6-18. INFINITY should be read.
RESULTS:
If  the  stator  fails  any  step  replace  it,  for  Steps  1-10 
keep  in  mind  resistance  values  may  vary  depending 
on  ambient  temperature  and  calibration  of  the  meter 
used.  If  the  stator  passes  all  tests  refer  back  to  the 
flow chart.
TEST 10 - SENSINg LEAdS
PROCEDURE:
1. Set a VOM to measure resistance.
2. Disconnect Connector C1. See Page 17 for connector location.
3. Locate the male side of the connector located on the bottom of
the control panel. See Figure 6-19. Connect one meter test lead
to Pin 1 Wire 11S. It may be helpful to connect a small jumper
lead to the individual pin. Connect the other meter test lead to
Wire 11S at Terminal Block 2 (TB2) . See Page 17 for Terminal
Block 2 location. Continuity should be measured.
PIN 
LOCATION
7
PIN 
LOCATION
6
PIN 
LOCATION
12
PIN 
LOCATION
1
0
4
77
66
55
6
2
77A
66A
55A
44S
11S
Figure 6-19. – C1 Connector, Male Side
4. Locate the male side of the connector located on the bottom
of the control panel. See Figure 6-19. Connect one meter test
lead  to  Pin  2 Wire  44S.  It  may  be  helpful  to  connect  a  small
jumper lead to the individual pin. Connect the other meter test
lead to Wire 44S at Terminal Block 2 (TB2). Continuity should
be measured.
5. Unplug the six pin connector at the Voltage Regulator.
6. Connect  the  one  meter  test  lead  to Wire  11S  at Terminal
Block 2 (TB2). Connect the other meter test lead to Wire 11S
at  the  six  pin  connector  previously  removed  from  the Voltage
Regulator. See Figure 6-11. Be careful not to damage the pin
connectors with the test leads. Continuity should be measured.
7. Connect  the  one  meter  test  lead  to Wire  44S  at Terminal
Block 2 (TB2). Connect the other meter test lead to Wire 44S
at  the  six  pin  connector  previously  removed  from  the Voltage
Regulator. See Figure 6-11. Be careful not to damage the pin
connectors with the test leads. Continuity should be measured.
RESULTS:
1. If  continuity  was  not  measured  in  any  of  the  steps  repair  or
replace wire.
2. If all steps pass refer back to flow chart.
section 6
Diagnostic tests
Page 44