Communication Manager Maintenance-Object Repair Procedures
958 Maintenance Procedures for Avaya Communication Manager 3.0, Media Gateways and Servers
 
Conference Circuit Test (#7)
The Conference Circuit test verifies that the NPE channel for the port being tested can correctly 
perform the conferencing function. The NPE is instructed to listen to several different tones and 
conference the tones together. The resulting signal is then measured by a tone detector port. If 
the level of the tone is within a certain range, the test passes.
2053
ABRT
At least one of the following errors is found on the DS1 circuit pack:
1281 – Loss of signal
1793 – Blue alarm
2049 – Red alarm
2305 – Yellow alarm
1537 – Hyperactivity
Look for the previous error types in the Hardware Error Log, and follow the 
procedures given in the 
documentation for the listed error types.
FAIL
The NPE of the tested port was found to be transmitting in error. This will 
cause noisy and unreliable connections.
1. Replace the circuit pack.
PASS
The port is correctly using its allocated time slots. User-reported troubles on 
this port should be investigated using other port tests and examining station, 
trunk, or external wiring.
Table 328: Test #6 NPE Crosstalk Test  (continued)
Error 
Code
Test 
Result
Description / Recommendation
 3 of 3
Table 329: Test #7 Conference Circuit Test 
Error 
Code
Test 
Result
Description / Recommendation
ABRT
System resources required for this test are not available.
1. Retry the command at 1-minute intervals up to 5 times.