Monessen Hearth CSDV20SLP Manuel D’Utilisation

Page de 44
58D6056
15
CSDV Series Direct Vent Gas Stove
VENTING INSTALLATION 
INSTALLATION FOR HORIZONTAL TERmI-
NATION 
1.  Determine the route your horizontal venting will take.
NOTE: The location of the horizontal vent termination on 
the exterior wall must meet all local and national building 
codes.
Snorkel terminations are available for terminations requir-
ing a vertical rise on the exterior of the building. Figures 14 
and 15. 
Follow the same installation procedures used for 
standard horizontal terminations. If installing the snorkel 
termination below grade (basement applications), you must 
provide proper drainage to prevent water from entering the 
snorkel termination. Figure 13. Do not back fill around the 
snorkel termination. 
ST1137
snorkel install
12” 
(305 mm)
Minimum
Snorkel
Figure 14 - 
Snorkel Termination
ST1137
12”
(305 mm)
Minimum
ST1138
snorkel drainage
Snorkel
Adequate 
Drainage
Figure 15 - 
Snorkel Termination 
with Drainage Pipe
ST1138
2.  Rigid  vent  pipes  and  fittings  have  special  twist-lock 
connections. Assemble the desired combination of pipe 
and elbows to the appliance adaptor with pipe seams 
oriented towards the wall or floor.
  Twist-lock  Procedure:  The  female  ends  of  the  pipes 
and  fittings  have  three  locking  lugs  (indentations). 
These  lugs  will  slide  straight  into  matching  slots  on 
the male end of adjacent pipes and fittings. Push the 
pipe sections together and twist one section clockwise 
approximately  one-quarter  turn  until  the  sections  are 
fully locked. Figure 16.
FP1953
rigid pipe
Female Locking 
Lugs
Male Slots
FP1953
NOTE: Horizontal runs 
of  vent  pipe  must  be 
supported  every  three 
(3)  feet  (914  mm).  Use 
wall  straps  for  this 
purpose.
Figure 16 -
Rigid Vent Pipe Connections
3.  Attach vent pipe assembly to the stove. Set stove in 
front of its permanent location to insure minimum clear-
ances. Mark the wall for a 9Z\x" (241 mm) square hole 
(for noncombustible material such as masonry block or 
concrete, a 7Z\x" [190 mm] diameter hole is acceptable). 
Figure 17. The center of the hole should line up with the 
center line of the horizontal rigid vent pipe. Cut a 9Z\x" x 
9Z\x" (241 x 241 mm) square hole through combustible 
exterior wall (7Z\x" [190 mm] diameter hole if noncom-
bustible). Frame as necessary. Figure 17
4.  Apply  a  bead  of  non-hardening  mastic  around  the 
outside edge of vent cap. Position the vent cap in the 
center of the 7Z\x" (190 mm) or 9Z\x" (241 mm) hole on the 
exterior wall with the word “UP” on the vent cap facing 
up.  Insure  proper  clearance  of  1"  to  combustibles  is 
maintained. Attach the vent cap with four wood screws 
supplied. Figure 18
For vinyl siding, stucco, or wood exterior use vinyl siding 
standoffs  between  vent  cap  and  exterior  wall. The  vinyl 
siding standoff prevents excessive heat from melting the 
vinyl siding material. Bolt the vent cap to the standoff. Apply 
non-hardening mastic around outside edge of the standoff 
instead of the vent cap assembly. Use wood screws pro-
vided to attach the standoff. Figure 19
NOTE: Replace the wood screws with appropriate fasteners 
for stucco, brick, concrete, or other types of siding.