Installation Instructions
CM2L40
11
Cable Installation and Routing
The CM2 has an integrated cable management system that
allows cables to be automatically "fed out" as the lift raises, and
"reeled in" as the lift lowers while maintaining constant cable
tension.
IMPORTANT ! :
The CM2 requires minimum cable lengths of
8 feet from display through lower mount.
To install cables:
1.
Remove two screws securing cable guide side cover. (See
Figure 17)
2.
Set hardware aside for reuse.
Figure 17
3.
Slide cable guide side cover away from mount and carefully
set aside. (See Figure 18)
Figure 18
4.
Loosen upper and lower cable clamps. (See Figure 19)
5.
Route cable(s) down through upper cable clamp.
(See Figure 19)
IMPORTANT ! :
Evenly distribute cables between the four
clamp locations to prevent tangling of cables and improper
operation of CM2.
IMPORTANT ! :
Leave enough cable length available above
upper cable clamp to allow the routing and tie-down of cables
between upper cable clamp and display.
6.
Route cable(s) down through opening behind cable pulley.
(See Figure 19) and (See Figure 20)
CAUTION:
DON’T TWIST CABLES! Damage to cables
may occur if cables are twisted during cable management.
Ensure that cables on rear side of CM2 (gray) stay
towards rear side of cable pulley. (See Figure 19)
and (See Figure 20)
Ensure that cables on front side of CM2 (black)
stay towards front side of cable pulley.  (See
Figure 19) and (See Figure 20)
x 2
1
Cable guide
side cover
3
Cable guide
side cover