Rinnai Infinity 32e Manuel D’Utilisation

Page de 40
39 
COMMISSIONING CHECK LIST 
For full details - Refer to Installation Instructions
Gas supply pipe is purged of foreign matter before connection.
For Hot and Cold cross connections i.e. Capped breaches/shower mixers,
taps closed and reversed ‘Flick Mixer’ connections?
That isolating valves are not connected directly to
the appliance and there is means of disconnection
after the isolating valve?
Have you cleaned cold water inlet filter?
That plumbing connections are correct?
Is appliance inlet gas pressure correct with all appliances operating?
Do the Master Controllers (if fitted) operate correctly?
Have you checked water temperature at all outlets?
Have you shown the customer how to operate the Temperature Controllers?
(If fitted)
Have you explained to the customer the minimum flow rate required to operate
the unit?
Have you explained to the Customer the Benefits of Controllers (If not fitted)
and that they can be added later?
Attention Installer - have you checked: