PILOT FLAME CHARACTERISTICS
The  correct  flame  will  be  blue  and  will  extend  beyond  the 
thermocouple. The flame will surround the thermocouple just below 
the tip. A slight yellow flame may occur where the pilot flame and 
main burner flame meet.
Figure 17
Oxygen Depletion Sensor Pilot (Figure 16)
When the pilot has a large yellow tip flame, clean the Oxygen 
Depletion Sensor as follows:
1.  Clean the ODS pilot by loosening nut B from the pilot tubing. 
When this procedure is required, grasp nut A with an open end 
wrench.
Warning: 
Never use needles, wires, or similar cylindrical objects to clean 
the pilot to avoid damaging the calibrated ruby that controls 
the gas flow.
2.  Blow air pressure through the holes indicated by the arrows. 
This will blow our foreign materials such as dust, lint and 
spider webs. Tighten nut B also by grasping nut A. 
MAIN BURNER OPERATION
Figure 18
The main burner operation is MANUAL. The owner must manually 
place the main burner in operation. The owner will either select 
one, three or five plaques to be in operation. Once the owner has 
turned the main burner ON, it will continue to operate until the 
owner manually turns the main burner OFF.
Description of Manual Gas Control Knob:
OFF position.
PILOT position.
SR-6
Position 1  Will have one plaque in operation, the input will be 
6,000 BTUH (1.8KW/H).
SR-10
Position 1  Will have one plaque in operation, the input will be 
10,000 BTUH(2.9KW/H).
SR-18
Position 1  Will have one plaque in operation, the input will be 
6,700 BTUH (2KW/H).
Position 2  Will have two plaques in operation, the input will be 
12,000 BTUH (3.5KW/H).
Position 3   Will have three plaques in operation, the input will 
be 18,000 BTUH (5.3KW/H).
SR-30
Position 1  Will have one plaque in operation, the input will be 
8,000 BTUH (2.3KW/H) for Natural gas and 7,000 
Btuh (2.1KW/H) for Propane/LP gas.
Position 2  Will have three plaques in operation, the input will 
be 18,000 BTUH (5.3KW/H).
Position 3  Will have five plaques in operation, the input will 
be 30,000 BTUH (8.8KW/H).