•  Battery charger connection to 120 VAC.
•  Communication wires connected between transfer 
switch and generator (HTS only).
•  Unit secured to pad.
START-UP CHECKLIST
  Before working on the generator, ensure the fol-
lowing:
• The AUTO/OFF/MANUAL switch is in the OFF 
position.
• The 120VAC supply to the battery charger is 
switched OFF.
PREPARATION FOR START-UP
•  Ensure that the 120VAC circuit breaker to the bat-
tery charger is open.
•  Remove the fuse from the the control panel. Open 
the front door of the control box and remove the 
15 Amp ATO fuse in the lower left-hand corner of 
the control box.
• Connect the battery cables to the battery. Attach 
negative battery cable last.
• Close the 120VAC circuit breaker to the battery 
charger.
•  Measure the voltage at the battery before and after 
the charger is turned on.
•  Verify all AC electrical connections are tight at the 
circuit breaker and transfer switch.
•  Visually inspect entire area looking for loose paper, 
plastic wrappings, leaves, etc.
• Check all hoses clamps fittings for leaks or dam-
age.
• Check all electrical plugs throughout the genera-
tor. Ensure each plug is seated correctly and fully 
inserted into its receptacle.
• Verify the AUTO/OFF/MANUAL switch is in OFF 
position.
‹
•  Open the valve to the engine fuel line.
•  Bleed the fuel system of air. (necessary for long fuel 
lines).
•  Open the generator main line circuit breaker.
• Connect a manometer to the gas line and record 
the static pressure. It must be as listed in the 
Specifications.
•  Insert the fuse into the control panel.
• Move the AUTO/OFF/MANUAL switch to the man-
ual position. The engine should now crank and 
start.
•  Check voltage at the generator terminals.
• For 3-phase units, check phase rotation at the 
transfer switch terminals. The generator phase 
rotation must match the utility phase rotation.
•  Check for coolant, fuel, oil, and exhaust leaks.
•  Close the generators main line circuit breaker.
•  Turn the generator set off.
• Connect the UTILITY supply to the transfer 
switch.
•  Set the AUTO/OFF/MANUAL switch to AUTO.
• Disconnect utility power before the transfer 
switch.
  Engine should start, transfer to load.
  Run at least 15 minutes on generator power. 
Make certain all 3-phase loads are functioning 
correctly (correct phase rotation).
• Reconnect Utility power
  Transfer switch will transfer back to Utility and 
engine will shut down within the given time 
parameters set up for the specific transfer switch 
and controller.
•  Install all covers, access plates and door panels.
• Put the Owners Manual in a safe and accessible 
place.
•  Make certain the AUTO/OFF/MANUAL switch is in 
the AUTO position.