Operating Instructions
29
4.0
O
PERATING
 I
NSTRUCTIONS
4.1
Startup Procedures 
Before the unit is placed into service after initial installation, after equipment relocation, or after 
equipment has been de-energized for an extended period of time, perform equipment inspection and 
and Startup Checklist.
After initial system startup, the following guidelines can be used for standard equipment operation. 
These guidelines should be reviewed for any special equipment modifications, special site consider-
ations or company policies that may require changes to the standard equipment operation.
4.1.1 Emergency Shutdown—If Emergency Power Off switch is supplied
To perform an immediate system shutdown during emergency conditions, lift the clear protective 
cover and push the Emergency Power Off (EPO) switch on the FPC’s monitoring panel.
If the site is equipped with a Remote Emergency Power Off (REPO) switch to perform an immediate 
room shutdown, actuate one of the REPO switches. NEC Article 645 requires a REPO switch at the 
principal exit doors.
4.1.2 Normal System Shutdown
To perform a normal system shutdown, perform an orderly load equipment shutdown according to the 
load equipment manufacturer’s recommended shutdown sequence. The load equipment can be turned 
OFF at each piece of load equipment or at the FPC’s output distribution (circuit breaker) panels 
located behind the FPC’s front door. Turn OFF all unit output breakers, then turn OFF the unit’s 
main input circuit breaker. To remove all power from the FPC, turn OFF the building power to the 
FPC’s input breaker or junction box.
4.1.3 Normal System Turn ON
Make certain all of the FPC’s circuit breakers are in the OFF position. All unit circuit breakers are 
located behind the front doors. Turn ON building power to the FPC. Turn ON the FPC’s main input 
circuit breaker. If the circuit breaker has been tripped OFF (instead of being turned OFF), the circuit 
breaker handle must be moved to the OFF position before being turned ON. If the FPC has a voltage 
monitoring panel, verify proper output voltages before turning ON output circuit breakers. Turn ON 
the panelboard main breakers. Individually turn ON each output circuit breaker following the load 
equipment manufacturer’s startup sequence.
4.1.4 Manual Restart
If the FPC’s manual restart feature has been selected, the unit’s main input circuit breaker will be 
tripped upon a power failure, preventing repetitive application of unstable voltage and allowing for an 
orderly system restart. If the main input circuit breaker is tripped upon a power failure, wait until 
power is restored, then follow the instructions in 4.1.3 - Normal System Turn ON.
NOTE
Depending on the particular control circuit wiring, operation of the unit EPO switch may cause 
other equipment to also shutdown.