Chapter 2.  Operation 
75 
 
This document is property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy 
Systems, North America, Inc.  Any copying, use, or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited. 
2.7.5 
Paralleling the Existing and ACU+ Power Systems 
Admonishments 
General Safety 
Danger:  YOU MUST FOLLOW APPROVED SAFETY PROCEDURES. 
 
Performing the following procedures may expose you to hazards.  These 
procedures should be performed by qualified technicians familiar with the hazards 
associated with this type of equipment.  These hazards may include shock, energy, 
and/or burns.  To avoid these hazards: 
a)  The tasks should be performed in the order indicated. 
b)  Remove watches, rings, and other jewelry. 
c)  Prior to contacting any uninsulated surface or termination, use a voltmeter to 
verify that no voltage or the expected voltage is present. 
d)  Wear eye protection, and use recommended tools. 
e)  Use double insulated tools appropriately rated for the work to be performed. 
AC Input Voltages 
Danger:  This system operates from AC voltage capable of producing fatal electrical shock. 
DC Input/Output Voltages 
Danger:  Connecting the ACU+ power system 
to an existing power system for “Power Split” 
mode involves working on live equipment carrying live loads. This system 
produces DC power and may require battery to be connected to it. Although the 
DC voltage is not hazardously high, the rectifiers and/or battery can deliver large 
amounts of current. Exercise extreme caution not to inadvertently contact or have 
any tool inadvertently contact a battery terminal or exposed wire connected to a 
battery terminal. NEVER allow a metal object, such as a tool, to contact more than 
one termination at a time, or to simultaneously contact a termination and a 
grounded object. Even a momentary short circuit can cause explosion and injury. 
Remove watches, rings, or other jewelry before connecting leads. Cover any live 
busbars with a canvas sheet to prevent short circuits caused by falling tools or 
parts. 
Preparing the Existing and ACU+ Power Systems 
 
Install and turn-up the ACU+ power system as describe in the installation instructions furnished with 
the power system. 
 
Set the float voltage on both the existing and ACU+ power systems to the same level.  Temperature 
compensation functionality, if used, should be disabled on both power systems. 
Paralleling the Systems 
 
Connect the Battery and Battery Return busbars of the ACU+ Power System to the main charge 
busbars (rectifier side of the shunt) on the parallel power system. Size the cable for the largest current 
between systems. 
Note 1:  The connections between the two power systems should be done with power cables 
appropriately sized to be capable of carrying the maximum current that can circulate 
between the two power systems.