Emerson M820D Manuel D’Utilisation

Page de 176
User Instructions 
UM1M820BNA 
Spec No. 1M820BNA (Model M820B) 
Issue AH, March 4, 2013 
Spec No. 1M820DNA (Model M820D) 
 
 
Chapter 2.  Operation 
79 
 
This document is property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy 
Systems, North America, Inc.  Any copying, use, or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited. 
2.7.7 
Verifying the Operation of the Power Split Feature 
After programming the “Power Split” feature, verify its operation as follows. 
a)  In a Power Split application where the ACU+ power system is taking all of the load and the rectifiers 
in the existing power system are all in the standby mode, use an external dry load bank of sufficient 
capacity to increase the load on the ACU+ power system 
over the “SLAVE CURRENT LIMIT” 
value. 
1)  Verify that the ACU+ power system limits the total output of its rectifiers to the current 
equivalent to this programmed percentage. 
2)  Verify that the ACU+ power system lowers its output voltage by the value of the programmed 
“DELTA VOLTAGE”. 
3)  Verify that the rectifiers in the existing power system take the additional load as the load 
increases pass the “SLAVE CURRENT LIMIT” value. 
4)  Further increase the load in order to exceed the total capacity of the rectifiers in the existing 
power system (or shut down some of the rectifiers in the existing power system if the capacity 
of the external dry load bank is not sufficient). Verify that the ACU+ power system starts taking 
the additional load as soon as the total capacity of the rectifiers in the existing power system is 
exceeded. 
b)  In a Power Split application where the ACU+ power system is taking only part of the load (operating 
continuously at the current level equivalent to the 
programmed “SLAVE CURRENT LIMIT” 
percentage) and the rectifiers in the existing power system are taking the rest of the load, use an 
external dry load bank of sufficient capacity to increase the load in order to exceed the total 
capacity of the rectifiers in the existing power system (or shut down some of the rectifiers in the 
existing power system if the capacity of the external dry load bank is not sufficient). 
1)  Verify that the ACU+ power system starts taking the additional load as soon as the total 
capacity of the rectifiers in the existing power system is exceeded.