4 – Installation
Installing a Switch
59096-04  A
4-13
A
To power up a SANbox 5000 Series switch, do the following:
„
For a model 5200/5600 switch, connect the power cord to the AC power 
receptacle on the front of the switch chassis and to a grounded AC outlet.
„
For a model 5202/5602 switch, connect the power cords to the power supply 
receptacles on the back of the switch chassis and to a grounded AC outlet. 
To provide redundancy in the event of an AC power circuit failure, connect 
the switch power supplies to separate AC circuits.
The switch responds in the following sequence:
1.
The chassis LEDs (Input Power, Heartbeat, System Fault) illuminate 
followed by all port Logged-In LEDs. The Logged-In LEDs that illuminate 
indicate the ports that are enabled.
2.
After a couple seconds the System Fault LED is extinguished while the Input 
Power LED and Heartbeat LED remain illuminated.
3.
After approximately one minute, the POST executes and the Heartbeat LED 
is extinguished.
4.
After about another minute, the POST is complete, all LEDs are 
extinguished except the Input Power LED and the Heartbeat LED:
„
The Input Power LED remains illuminated indicating that the switch 
logic circuitry is receiving DC voltage. If not, contact your authorized 
maintenance provider.
„
The Heartbeat LED indicates the results of the POST. The POST tests 
the condition of firmware, memories, data-paths, and switch logic 
circuitry. If the Heartbeat LED blinks steadily about once per second, 
the POST was successful, and you can continue with the installation 
process. Any other blink pattern indicates that an error has occurred. 
Refer to 
 for more 
information about error blink patterns.