Chapter 3: Installation 
22 
Chapter 3: Installation
 
3-1  Uncrating the Equipment 
Continuous loss-in-weight blenders are shipped bolted on a skid, enclosed in plastic wrap, 
and contained in a wood crate. 
1.  Remove the crate from around blender. 
2.  Secure strap of proper lifting capacity to the lifting lugs installed in the holes 
provided. 
Caution! 
Use approved safety straps or chains to lift the blender from the eyebolts on 
the top plate (See figure 6 below for eyebolt positioning). 
 
 
 
Figure 6:  Lifting Eyebolt Position on Blender 
 
 
 
Caution! 
Remove hoppers if necessary to prevent damage. 
3.  Lift blender until strap is taut. 
4.  Remove bolts attaching bottom of blender to shipping skid. 
5.  Raise the blender slowly. 
 
3-2  Rigging and Placing the Unit 
It is the intent of this section to familiarize the reader with the proper site requirements and 
installation procedures of the continuous loss-in-weight blending system. The information in 
this section is NOT meant to replace or supersede an established local or company 
implemented procedures. It is meant to enhance them. 
Note:  The manufacturer assumes NO responsibility for any damages resulting from 
improper installation, or improper handling during the installation process.