Hussmann proto-aire Manuel De Montage

Page de 124
Protocol™ Installation and 
Service Manual 
Service and Maintenance 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
IMPORTANT:  Since Hussmann has no direct control over the installation, 
providing the freeze-burst protection is the responsibility of the installing 
contractor.  
Refer to Page 2-4
 
 
Know whether or not a circuit is open at the power supply.  Remove all power 
before opening control panels.
  Note:  S
OME EQUIPEMENT HAS MORE THAN ONE 
POWER SUPPLY
 
Always use a pressure regulator with a nitrogen tank.  Do not exceed 2 psig and 
vent lines when brazing.  Do not exceed 350 psig for leak testing high side.  Do not 
exceed 150 psig for leak testing low side. 
 
Always recapture test charge in approved recovery vessel for recycling. 
 
The Water Loop should be tested for leaks using pressurized water. 
DO NOT exceed 75 psig. 
Service 
 
Compressor Replacement 
 
Before beginning removal of old compressor prepare replacement compressor as 
follows: 
 
 
 
Verify 
Replacement compressor 
  Electrical 
requirements 
 Refrigerant 
application 
  Capacity 
 
Piping hookup location and design 
 
 
Suction and discharge gaskets 
 Mounting 
requirements 
 
Have compressor in an easily accessible position, uncrated and unbolted from 
shipping pallet. 
 
 
Disconnect Electrical Supply 
Turn off motor and control panel power supplies to the Unit. 
 
Turn off control circuit and open all compressor circuit breakers. 
 
Tag and remove electrical wires from the compressor. 
 
 Isolate 
Compressor 
 
115