Water Loop Piping
Important:
Since Hussmann has no direct control over the installation, providing
freeze-burst protection is the responsibility of the installing contractor.
It is
mandatory that glycol be added to the water loop before startup to prevent
freezing. Use only non-ferrous metal or PVC for water loop piping.
freezing. Use only non-ferrous metal or PVC for water loop piping.
The Water Loop should be tested for leaks using pressurized water.
DO NOT exceed 75 psig
Overview
This section details major water loop components, and their locations in the piping system.
Water Loop Guidelines
Pipe Connections
PVC Plastic pipe should be solvent welded (glued) together as described on the glue can.
Pipe Fittings must be clean and dry.
Cut Pipe with a guillotine type cutter to get a clean, square cut; remove any burrs.
Use Purple Primer on both pipe and fitting before gluing.
Apply glue to both pipe and fitting and join with a twisting motion.
Hold joint together for approximately 30 seconds to allow glue to set.
Allow to dry for 24 hours before putting in to service.
Where it is necessary to connect plastic and metal pipe. DO NOT USE A THREADED
CONNECTION. A compression type fitting should be used. For larger pipe sizes, a
flanged connection may be used.
Isolation Valves
Install isolation valves at inlet and outlet of each Protocol™ unit.
It is good practice to include isolation valves at several locations throughout the piping.
For example valves should be used where branches tie into main supply and return lines.
PVC plastic ball valves may be used.
Strainers
Use a 16-mesh strainer at inlet of each Protocol™ unit. Position isolation valves so that
this strainer can be opened for cleaning.