Cisco Aironet 1300 Series Lightweight Outdoor Access Point Mounting Instructions
78-17634-01
Mounting the Access Point
Step 6
Connect the cables to the access point (or lowest grounding block on the tower). The cables should slope 
downward so that moisture runs away from the connectors during rainstorms. If necessary, form drip 
loops near the connectors.
Step 7
Cut the cables to length, install F-connectors on the ends, and connect them to the grounding block.
Step 8
Weather seal all coaxial connectors by wrapping them with the sealant tape provided with the installation 
kit. For more information, see the 
.
Mast Mount
Mounting the access point on a tall mast makes antenna positioning difficult because you cannot view 
the access point LEDs or adjust the antenna vertically. If possible, use a mast short enough so that you 
can reach the access point from a step ladder or other support. Otherwise, you may need to take down 
the mast to adjust the antenna position.
Mounting the access point on a mast includes the following subtasks:
1.
Preparing the mast
2.
Mounting the access point
3.
Routing mast cables
4.
Raising the mast and connecting cables
This warning applies to outdoor installations.
Warning
Only trained and qualified personnel should be allowed to install, replace, or service this equipment. 
Statement 1030
Preparing the Mast
To prepare the mast, follow these steps:
Step 1
Choose a mounting location for the mast. For more information, see the 
Step 2
Find a solid mounting position on the building for the mast mounting bracket, such as a stud or main 
building member on a roof or external wall. Use a stud finder, if necessary, to find wooden structural 
members. 
Step 3
Find the mast-mounting hardware and guy wire.
Step 4
Find and install the guy line mounting points. A minimum of three, preferably four, guy lines should 
hold the mast in position.
Step 5
Measure the length of the guy lines by attaching the lines to the mast at their mounting point and 
unspooling them to the attachment points.
Step 6
Raise the mast to its vertical position and temporarily secure all guy lines to their mounting points.
Step 7
Ensure that the mast is vertical using a level on two sides (90 degrees apart) of the pole. Adjust guy lines 