10
 
4.0
 
I
NSTALLATION
 
 
This section contains installation recommendations, unpacking, inspection, and 
installation instructions for the Technalogix P-379 Processor. Carefully read all material 
in this section prior to installation. Also read and review operating procedures later in this 
section. 
Building Recommendations 
The quality of the building is of great importance if you are to expect long life and 
continued performance from the processor. The building must be clean, dry, temperature 
controlled and secure. The processor takes up a single 1-U high space on a 19” rack. 
Don’t forget to allow space in the building for any additional racks to house test 
equipment, a workbench area, line regulating transformers, ladders, equipment and 
parts storage, first aid kit, emergency generator if used, as well as heating and cooling 
devices that may be unique to your installation. A sloping roof will tend to develop leaks 
less rapidly. The building should be well roofed with good material. The cooling load will 
be lowered with reflective or light colored roofing material. 
Heating and Cooling Requirements 
 
The environment’s temperature will contribute greatly to the length of the processor’s 
life. Technalogix recommends that the building’s filtered air intake must have capacity for 
all air-flow in the building plus an additional 20%.  Keep the intake below the roofline to 
avoid intake of solar heated air. Please ensure that the intake and exhaust areas are on 
the same side of the building to avoid pressure differentials during windy conditions. 
Also, do not position intake near exhaust’s preheated air. If air conditioning is required to 
cool the shelter, discuss the situation with a qualified HVAC technician. Under average 