Z Com Inc ZC3625-55V04 Manuel D’Utilisation

Page de 33
 
Chapter 3 Hardware Installation 
Page 14
Chapter 3 Hardware Installation 
The ZC-3625-55-23 Wireless Bridge is shipped with mounting hardware that accommodates 
tower or mast installations. This chapter demonstrates the hardware installation procedures, 
which include Assemble the Hardware Mounting, Pole Mounting, Connect Up, Ground the 
Wire, Power On and Align the Antennas. 
Assemble the Mounting Bracket 
1.  Assemble the main bracket by placing articulation pole to the T-form bracket via a 
M8×110 screw through the insertion axe and fix with the M8 washer, spring washer and 
M8 nut; 
 
 
2.  Place the main bracket into the seating and use a spanner to fasten the bracket to CPE 
main unit with M5×12 screws and M5 washers provided in hardware packets;