ADC Telecommunications Inc. F0694-011 Manuel D’Utilisation

Page de 234
Fusion Wideband Installation Procedures
7-36
InterReach Fusion Wideband Installation, Operation, and Reference Manual
CONFIDENTIAL
D-620616-0-20 Rev D
7.4.4
Configuring the Fusion Wideband System
Before the system can operate properly, use AdminBrowser to program the Fusion 
Wideband Main Hub with the frequency bands that are to be distributed. The Hub 
must be programmed with the same frequencies as the RAU used.
NOTE: The frequency bands should automatically be set on power up and 
this step should not be required.
Considerations:
• The AdminBrowser software, described in the AdminBrowser User Manual 
(PN D-620607-0-20), must be running on a PC/laptop.
• Crossover Ethernet cable with male connectors required.
Connecting a PC to the Main Hub to Run AdminBrowser
1.
Connect the AC power cord to the Hub.
Make sure the Hub is grounded through the ground lug on the AC power and 
the frame ground lug as required. The warranty does not cover damage 
caused when an ungrounded Hub is powered on.
2.
Plug the power cord into an AC power outlet.
3.
Verify that all cables are properly connected on the Hub.
4.
Turn on the power to the Hub.
Table 7-7
Troubleshooting RAU LEDs During Installation
During
Installation
LED
State
Action
Impact
The RAU is connected 
to the Fusion Wide-
band Expansion Hub, 
which is powered on
LINK
Off
Check CATV cable.
No power to the RAU.
ALARM
Off
LINK
Green
• Check CATV cable
• Check Hub LEDs
• Use AdminBrowser to determine the 
problem.
The RAU is off-line.
ALARM
Red
LINK
Red from 
green, after 
cables are 
connected for 
60 seconds
• Check CATV cable.
• Check the Hub LEDs.
• Use AdminBrowser to determine the 
problem.
No communications 
between the RAU and the 
Hub.
ALARM
Red