Once the legacy pedestals are removed, you are ready to install the new Liberty UHX
pedestals.
The installation of the new Liberty UHX pedestal includes the following:
• Cutting a new wiring channel
• Running the electrical and network wiring
• Installing the new Liberty UHX pedestal
Placement of the Liberty UHX pedestals coincides with normal placement of the Liberty
The installation of the new Liberty UHX pedestal includes the following:
• Cutting a new wiring channel
• Running the electrical and network wiring
• Installing the new Liberty UHX pedestal
Placement of the Liberty UHX pedestals coincides with normal placement of the Liberty
PX pedestals.
Cutting new wiring channel
Checkpoint contractors will cut floor trench in the center of existing EAS pedestal
infrastructure and back fill trench upon completion of wire installations.
Estimated completion time
The cutting of a 35-foot floor channel will take approximately 60 minutes. This can vary