Verify site preparation completed
Overview
This topic describes what must be done to verify that the site preparation is complete so
that installation procedures can begin.
If some of the requirements are not met, the installer must do so now.
Verify site preparation
Before installation of the RRH site can begin, site preparation should have been
completed in accordance with Alcatel-Lucent FDD Remote Radio Head (700 MHz) Site
Preparation Guidelines, 
418-000-424.
This unit is only to be installed in restricted access locations.
The following site preparation requirements must be met before the installation of the
RRH can begin:
• Adequate clearance must be provided for service access.
• DC electric service must be installed.
• User alarm facilities must be installed.
• Grounding electrode system must be installed.
• RF and antenna runs must be installed.
• Surge protection for antennas must be installed (if required).
• Tower light power must be installed (if required).
• Tower light alarm must be installed (if required).
• Mounting bracket holes must be drilled.
• The environment must comply with limits listed under Environmental Requirements.
• Cable supports and racks must be installed.
• Conduits for user alarms, and power are provided.
Tools, materials, and checklist
Preparatory information
Verify site preparation completed
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
4-8