Andrew Wireless Innovations Group BCEL-FAST900 Manuel D’Utilisation
MN021-01
Page 22 of 28
18. Technical support
Our on-line help desk at
www.tekmar.it
gives immediate access to our team of Experts, who
are committed to providing you with the best service in the shortest possible time.
For further information on the product, not described in this publication, you can contact our
Project Implementation & technical support team at
For further information on the product, not described in this publication, you can contact our
Project Implementation & technical support team at
helpdesk@tekmar.it
APPENDIX
19. Appendix A : Installation checklist
The following checklist provides a summary of the procedures for installing a BriteCell™ Fast
system.
Step
Item/ Action
Description
♦
♦
1
BriteCell™ Fast Site Drawing
Master copy of the site plan noting the remote
locations and serial numbers, and the location of
the indoor coverage antenna(s). This should
characterize the design parameters for the
system including cable paths and lengths.
locations and serial numbers, and the location of
the indoor coverage antenna(s). This should
characterize the design parameters for the
system including cable paths and lengths.
2
Equipment List:
Quantity & serial numbers:
BriteCell™ Fast Donor
BriteCell™ Fast Remotes
AC Power Source
AC Power Outlet
Coverage Antenna(s)
Input coaxial cable
Coverage Antenna Cables
3
Installation tools:
Cable connector Tools*
Crimper, knife, etc.
Multimeter
To ensure no cable shorts.
Handset with Power Indicator
To verify coverage after commissioning.
4
Run Cable
Install Cable in the site.
5
Attach Connectors*
Measure resistance across center pin and outer
shell (ground) to ensure no short.
shell (ground) to ensure no short.
7
Record Serial Numbers and
Locations on site Drawing.
Locations on site Drawing.
Note: this is to help Technical Support
Specialists, should you need their assistance.
Specialists, should you need their assistance.
8
Mount the Equipment
Including indoor coverage antennas.
9
Connect the coaxial cables as
shown on the Site Plan
shown on the Site Plan
Use caution when connecting semi-flexible
cables to the mounted BriteCell™ Fast and
antennas. Excessive force on antenna or
BriteCell™ Fast connectors will result in serious
equipment damage.
cables to the mounted BriteCell™ Fast and
antennas. Excessive force on antenna or
BriteCell™ Fast connectors will result in serious
equipment damage.
10
Supply AC Power, and
commission the System.
commission the System.
Check the BriteCell™ Fast status LED’s.
11
Check Power Levels
Check power indication of handheld mobile at
various locations within the coverage area.
various locations within the coverage area.
* As Required