 Chapter 
Maintenance 
 
6.5.6.2 
Air-to-Air Heat Exchanger/Heater Installation 
 
The replacement air-to-air heat exchanger/heater should be installed in HB cabinet or LB 
cabinet in the following sequence: 
 
1.  Before the replacement air-to-air heat exchanger/heater is installed, ensure that the 
weatherproof gasket is placed on the side of the air-to-air heat exchanger/heater that 
will rest against the side of the cabinet – see Figure 6-11
2.  Using two handlers, one located on each side of the air-to-air heat exchanger/heater, 
carefully lift the air-to-air heat exchanger/heater and place it in the opening in the 
side of the cabinet. 
3.  Replace the twelve (12) 1/4-20 socket head cap screws (with 1/4” flat washers and 
gaskets) which secure the air-to-air heat exchanger/heater to the cabinet – see Figure 
  A torque rating of 45.6 Inch Lbs. must be used to tighten the screws.
 
4. 
Install four (4) cable tie mounts on the air-to-air heat exchanger/heater inside panel 
5.  Secure the two (2) temperature sensor cable assemblies (ELECTR COMP AIR INTAKE 
and ELECTR COMP AIR EXH) to the cable tie mounts located on the air-to-air heat 
exchanger/heater inside panel – see Figure 6-9. 
6.  Re-connect the 8-pin pluggable terminal block to the air-to-air heat exchanger/heater 
inside panel 8-pin terminal block receptacle – see Figure 6-9. 
7.  Switch ON the HE circuit breaker (CB 5), located on the HB cabinet PDU or LB cabinet 
PDU. 
8.  Close the electronics compartment front and rear doors. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
SX03-20000-01-M01 6-25