Baicells Technologies Co. Ltd. MBS1105 Manuel D’Utilisation
Baicells mBS1105 Base Station Installation Guide(V100R001C00,02).docx
9
Figure 3-1 Installation Space Requirement
Personnel Requirements
3.4
The installation personnel must master the basic safe operation knowledge, through the
training, and having the corresponding qualifications..
Lightening and Grounding Protection
3.5
CAUTION
:
It is unlikely to happen but since the LTE eNodeB is very sophisticated equipment
so we would recommend you to test it on the ground to make sure everything is
functioning before install on the tower.
The operator must prepare external lightning protector to protect the GPS, external
antenna and RJ-45 port.
Grounding Notes:
The ground wire adopts yellow-green wire that is no smaller than 16 mm².
Grounding principle: as near as possible.
The eNodeB connects to the reliable outdoor grounding point (earth) through one
ground screw.