HP Performance Optimized Data Center (POD) 40cp Guide De Montage

Page de 21
 
Site requirements  5 
• 
You have chilled water at your final location. 
• 
You have made provisions for properly grounding the HP POD. 
 
System utilities 
Your site location must accommodate the following utilities: 
• 
Cooling water 
• 
Electrical power ("
" on page 
) 
• 
Drainage (on page 
) 
 
Power 
 
 
Item 
Description 
Main input power junction box 
Chilled water return connection 
Chilled water supply connection 
IT cable portals