Pre-Power-Up Check 
 
Copyright © 2005-2006 Eaton Corporation.  All Rights Reserved. 
IPN 997-00012-41D    December 2006 
4-3
 
Pre-Power-Up Check 
Use the checklist below to complete initial checks before progressing further. 
 
Checklist 
…
  All AC and DC cabling is installed 
 
…
  All cabling is neat and correctly insulated 
 
…
 
DC battery and load cabling has the correct polarity 
 
…
 
All panels are in place and all empty rectifier slots are covered 
with blanking panels 
 
…
 
The AC supply to the power system is switched OFF 
 
…
 
All circuit breakers at the front of the power system are 
switched OFF 
 
…
 
Batteries (if fitted) are isolated from the power system