HP Performance Optimized Data Center (POD) 20cp Guide D’Installation Rapide

Page de 38
 
Site plan requirements and actions  23 
• 
Ensure that the site safety and security programs are properly administered. 
• 
Interface directly with the HP installation project manager to ensure clear lines of communication during 
the installation and commissioning processes. 
 
Site planning 
A comprehensive site plan assists with the site design (MEP) and ensures the best possible HP POD 20c 
installation process. When creating a site plan, consider the following information: 
• 
HP POD 20c site requirements detailed in this document 
• 
HP POD 20c site preparation drawing package 
• 
HP POD 20c readiness checklist ("
" on page 
) 
• 
HP POD 20c installation (on page 
) 
The HP team can assist you by answering questions and help to guiding you throughout the process. 
 
HP POD 20c installation 
HP POD 20c installation includes the following: 
• 
Installation equipment staging (on page 
) 
• 
HP POD 20c lifting layout (on page 
) 
• 
HP POD 20c storage requirements (on page 
) 
• 
Additional structures (on page 
) 
 
Installation equipment staging 
Staging for the following items must be identified and considered: 
• 
Truck and component staging 
• 
Installation equipment staging 
• 
Site traffic 
• 
Regulatory or local permits 
 
HP POD 20c lifting layout 
When preparing a site plan, identify where to place the HP POD 20c and the equipment that is used for 
assembly. The following figure shows an HP POD 20c assembly site and includes: 
• 
HP POD 20c location 
• 
Crane location