P R E P A R A T I O N
assembly
After the machine is placed in the final location, 
and before the lifting apparatus is removed, 
you should install the machine feet. Included 
with your machine are four cushioned feet with 
built-in adjustment studs (see Figure 7). These 
feet are easily installed and provide for accurate 
machine leveling.
To install the feet:
1.  Using lifting equipment and wooden blocks, 
raise and support the machine base so there 
is approximately 5" between the floor and 
underside of the base.
2.  Remove the jam nuts from the foot studs.
3.  Apply any general-purpose automotive 
grease to the stud threads.
4.  Thread the studs into the machine base 
from the bottom up until the studs emerge 
from the cabinet floor approximately 2" (see 
Figure 7).
Figure 7. Machine feet.
Foot Stud
Jam Nut
Threaded 
Hole
Machine 
Foot
5.  Thread the jam nuts onto the protruding 
studs but do not tighten them at this time. 
6.  Place the machine onto the floor. 
7.  Using a precision level on the machine table, 
adjust the feet studs, so the machine is level 
from side-to-side and front-to-back.
8.  Use a 19mm wrench to tighten the jam nuts 
inside of the cabinet and lock the feet studs 
into place.
Note: Over the course of the next six months, 
periodically verify that the machine is still 
level, and re-adjust the feet as required.
9.  Rotate the top handwheel counterclockwise 
to raise the headstock slightly. Then remove 
the wood support block (see Figure 8).
Figure 8. Support block.
10.  Using a 14mm wrench, install the two 
handles into the handwheels (Figure 9).
Figure 9. Headstock height handwheel.