Chief Personal Lift SL220 Manuel D’Utilisation

Page de 20
Installation Instructions
SL220
7
Securing SL220 Frame to Ceiling Structure
1.
Examine ceiling structure (concrete, steel truss, or wood)
above SL220 frame (B)  to identify four support cable
anchor locations.  Each location should be approximately
15° outside of support holes in SL220 frame (B). Mark
locations with pencil. (See Figure 4).
Figure 4
Solid Concrete Ceiling Structure
WARNING:
Anchors must be installed into structurally
sound solid concrete with a minimum thickness of 1.75"
(44.5mm) or greater.  Installation into hollow concrete block,
mortar, or concrete that exhibits cracking, spalling, or other
defects may result in failure of anchor and serious personal
injury or damage to equipment!
1.
Drill 1/4" diameter x 1-1/8" deep pilot hole at each marked
cable anchor support location.  Ensure hole is at least
2-1/2" from nearest concrete edge.  Remove debris from
hole. (See Figure 5)
Figure 5
2.
Tap anchor (J3) into each hole to a depth of at least 1". (See
Figure 5)
WARNING:
Failure to properly set anchor may result in
failure of anchor and serious personal injury or damage to
equipment!
3.
Using claw portion of hammer, set each anchor (J3) by
pulling it out of hole approximately 1/4". (See Figure 5)
4.
Insert portion of manufactured loop on cable (J1) through
hole in anchor (J3), and insert end of cable (J1) through
loop. Repeat for 3 remaining support locations.
(See Figure 5)
Steel Truss Ceiling Structure
1.
Route end of cable (J1) over truss at marked cable anchor
support location and then through cable loop.  Repeat for 3
remaining support locations. (See Figure 6)
Figure 6
x 4
15°
15°
x 4
x 4
1
x 4
(B)
1
2
3
4
1/4"
(J3)
(J1) x 4
(J1) x 4
1