Force10 Networks Force10 TeraScale E-Series E1200i Manuel D’Utilisation

Page de 105
Installing and Maintaining the E1200i System
37
AC Power Supply and Fan Operability Test 
Once your power supplies and fan trays are installed, verify their operability by supplying power to the 
chassis and verifying the status LEDs. 
Before you begin this power test, inspect your equipment rack and chassis. Verify that: 
Each Power Supply is properly installed and plugged into the assigned slot. 
The AC-cord Retainer is secured over the plugs. 
Your power cables connect to an appropriate AC power supply in a manner that complies with your 
local electrical codes. For AC systems, a Main Disconnect must be provided for each AC cord.
3.
Slide the power supplies into their slots until the module front is flush with the shelf front.
Figure 13   Insert power supply
4.
Connect the Power Supply cord to the designated socket (
5.
Re-install the AC-cord Retainer by tilting approximately 15
o
 and gently sliding in the long edge just above 
the AC cords.
6.
Secure the retainer by tighten the locking screws on either side of the retainer.
Danger: Leakage Current (High Touch Current) in AC-powered systems: AC power cords are 
secured to the power inlet using the provided brackets. The power cord plugs must be secured to 
the building outlets by the qualified chassis installer or a qualified electrician.
Danger: Prevent exposure and contact with hazardous voltages. Do not attempt to operate this 
system without the AC-cord Retainer.
Step
Task (continued)