Installing Support Brackets (Figure 63)
A  horizontal  pipe  support  MUST  BE  used  for  each  3  feet  of 
horizontal run. The pipe supports should be placed around the  pipe 
and nailed in place to framing members. There MUST BE a 3 inch 
clearance to combustibles above 6 ⅝ inch diameter pipe and elbows 
and 1 inch clearance on both sides and bottom of 6 ⅝ inch pipe to 
combustibles on all horizontal pipe sections and elbows. 
Vertical runs of this vent systems must be supported every 4 feet 
above the appliance flue outlet by wall brackets attached to the 
6 ⅝ inch vent pipe and secured with nails or screws to structural 
framing members.
 
Figure 63
Installing Firestops (Figures 64, 65, 66 and 67)
Firestops are required for safety whenever the vent system passes 
through an interior wall, an exterior wall, or a ceiling. These firestops 
act as a firebreak heat shield and as a means to insure that minimum 
clearances are maintained to the vent system.
Horizontal runs in the vent system which pass through either interior 
or exterior walls, require the use of wall firestops on both sides of 
the wall through which the vent passes.
Position the firestops on both sides of the 10 inch x 11 inch hole, 
previously cut. Secure with nails or screws. The heat shields of the 
firestops MUST BE placed towards the top of the hole. Continue 
the vent run through the firestops. See Figure 64.
10”
11”
Figure 64
Vertical runs of this system which pass through ceilings require the 
use of ONE (1) ceiling firestop at the hole in each ceiling through 
which the vent passes.
Position a plumb bob directly over the center of the vertical vent 
component and mark the ceiling to establish the center point of the 
vent. Drill a hole or drive a nail through this center point and check 
the floor above for any obstructions such as wiring or plumbing 
runs. Reposition the appliance and vent system, if necessary, to 
accommodate ceiling joists and/or obstructions.
Cut a 10 inch x 10 inch hole through the ceiling, using the center 
point previously marked. Frame the hole with framing lumber the 
same size as the ceiling joists. See Figure 65. If the area above the 
ceiling is NOT an attic, position and secure the ceiling firestop on 
the ceiling side of the previously cut and framed hole. See Figure 
66. If the area above the ceiling is an attic, position and secure the 
firestop on top of the previously framed hole. See Figure 67.
NOTE:
 Remove insulation from the framed area in the attic before 
installing the firestop and/or vent pipes.
6 ⅝" VENTING FRAMING AND FINISHING