Vertical  Sidewall Installation
Twist Lock Pipe
STEP 1
Locate vent opening on the wall. It may be necessary 
to first position the fireplace and measure to obtain hole 
location. Depending on whether the wall is combustible 
or noncombustible, cut opening to size. (Fig. 33) (For 
combustible walls first frame in opening.)
NOTE: When using flex vent, the opening will have to 
be measured according to the 1/2” (13 mm) rise in 12” 
(305 mm) vent run.
Combustible Walls (Fig. 33): Cut a 9³⁄₈”H x 9³⁄₈” W 
(240 x 240 mm) hole through the exterior wall and 
frame.
Noncombustible Walls (Fig. 33): Hole opening must 
be 7.5” (190 mm) in diameter. 
VO584-100
Vent Opening
2/99   djt
Vent Opening for Combustible Wall
9³⁄₈”
(240 mm)
9³⁄₈”
(240 mm)
Fireplace Hearth
Framing 
Detail
Opening for Noncombustible Wall
7¹⁄₂”
(190 mm)
VO584-100
Fig. 33  Locate vent opening on wall.
ZCS101 
Zero Clearance Sleeve
3/11/99   djt
Max. Length 
12” (305mm)
#8 Screws (2)
#8 Screws 
(2)
Adjustable 
Zero Clearance 
Sleeve
#8 
Screws 
(2)
Adjustable Zero Clearance Sleeve
ZCS101
Fig. 34  Adjustable zero clearance sleeve.
Firestop
STEP 2
Measure wall thickness and cut adjustable zero clearance 
sleeve parts to proper length (MAXIMUM 12”/305 mm). 
Assemble sleeve and attach to firestop with #8 sheet metal 
screws (supplied). Install firestop assembly. (Fig. 34)
Zero clearance sleeve is only required for 
combustible walls.
STEP 3
Place fireplace into position. Measure the vertical height 
(X) required from the base of the flue collars to the 
center of the wall opening. (Fig. 35)
STEP 4
Apply a band of silicone to the inner and outer flue 
collars of the fireplace and using appropriate length of 
pipe section(s) attach to fireplace with three (3) screws. 
Follow with the installation of the inner and outer elbow, 
again secure joints with three (3) sheet metal screws. 
Wipe off any excess silicone.
STEP 5
Measure the horizontal length requirement including a 
2” (51 mm) overlap, i.e. from the elbow to the outside 
wall finish plus 2”, or the distance required if installing a 
second 90° elbow. (Fig. 26)
Always install horizontal venting on a level 
plane.
STEP 6
Use appropriate length of pipe section - telescopic or 
fixed - and install. The sections which go through the 
wall are packaged with the starter kit, and can be cut to 
suit if necessary.
Sealing vent pipe and firestop gaps with high tem-
perature sealant will restrict cold air being drawn in 
around fireplace.