Sterling SSE-5 BL Manuel D’Utilisation

Page de 61
SSE 5 BL
Putting into operation 3-3
3.2.  Adjusting the suction pipes
The suction pipes have to be adjusted exactly to ensure troublefree operation.
1. Set the suction pipes to their home position.
&
 
At home position the inner pipe of the suction pipe protrudes
about 120-160 mm (4.75" - 6.25") from the outer pipe at the top
end.
2. Start a conveying operation.
Connect the unit to mains supply by the device plug.
3. Observe the flexible hose at the suction pipe.
The flexible hose must not show any pulsating movement
4. Observe the flexible hose at the separator.
The conveying hose must only move during in-feed.
If the conditions (points 3 + 4) are not met:
Pull the inner pipe further out of the outer pipe until there is no more jerky conveyance.
If the conditions (points 3 + 4) are met:
Push the inner pipe slowly into the outer pipe until pulsating of the flexible hose or shock
conveyance occurs.
Now pull the inner pipe slightly back again until the hose stop pulsating.
Select a setting between the two pipes to ensure that enough air can flow into the material pipe.
Once you have reached a satisfactory conveying result turn the wing screw at the suction pipe
tight.