ELECTRICAL POWER SUPPLY
Conduit Runs
Control Wires
     Run #1
Autoflow Control Box to Master
Fan/Heater Control Box
Five (5)-Control  wires 16ga minimum
    (NOTE: A shielded two conductor 16ga cable should
     be used for the network connections.)
     Run #2
Autoflow Control Box to Actuator
Control Box
Five (5)-Control  wires 16ga minimum
     Run #3
Autoflow Control Box to Wet
Supply Rotary Switch
Four (4)-Control wires 16ga minimum
     Run #4
Autoflow Control Box to Storage
Chamber Rotary Switch
Five (5)-Control  wires 16ga minimum
     Run #5
Autoflow Control Box to Drying
Chamber Rotary Switches
Six (6)-Control wires 16ga minimum
     Run #6
Autoflow Control Box to Fill
System Control  Box (if applicable)
Ten (10)-Control wires 16ga minimum
     Run #7
Master Fan/Heater Control Box to
Slave Fan/Heater Control Box
Four (4)-Control wires 16ga minimum
     (NOTE: A shielded two conductor 16ga cable should
      be used for  the network connections.)
     Run #8
Slave Fan/Heater #1 Control Box to
Slave Fan/Heater #2 Control Box
Four (4)-Control wires 16ga minimum
     (NOTE: A shielded two conductor 16ga cable should
      be used for the network connections.)
Power/Motor Wires
    Run #1
Entrance Panel to Master Fan/
Heater Control Box (for fan
motor)
     Run #2
Entrance Panel to Slave Fan/
Heater Control Boxes (if
applicable, for fan motor)
     Run #3
Entrance Panel to Fill System
Control Box ( if applicable)
-For Fill System #1 motor starter
-For Fill System #2 motor starter
(if applicable)
-For Aeration fan motor starter
     Run #4
Fill System Control Box to Fill
System #1 Motor
     Run #5
Fill System Control Box to Fill
System #2 Motor ( if applicable)
     Run #6
Fill System Control Box to
Aeration Fan Motor
     Run #7
Entrance Panel to Actuator
Control Box
-110V AC, 110V N, Ground wire
for battery charger
                     Grounding
All Control Boxes should be properly
grounded with a ground lug mounted in each control
box.