Empire Products GWT-35-2 Manuale Utente

Pagina di 20
Page 8 
  12425-7-0406  
  1.  In  selecting  a  location  for  installation,  it  is  necessary  to 
provide adequate accessibility clearances for servicing and 
proper installation.
  2.  Clearances  to  combustible  surfaces  are  4"  (102mm)  from 
sides, 12" (305mm) to top, 1 1/2" (38mm) from floor.
VENTILATION AND COMBUSTION AIR
Wall furnaces shall be installed in a location in which the facilities 
for ventilation permit satisfactory combustion of gas and proper 
venting under normal conditions.  In buildings of conventional 
frame, brick, or stone construction without tight storm windows 
and doors, infiltration is normally adequate to provide air for 
combustion and draft hood dilution.
Where appliances are installed in confined and unconfined spaces 
within a building, the building being of unusually tight construction, 
air for combustion and ventilation must be obtained directly from 
outdoors or from such spaces that freely communicate with the 
outdoors.  Under these conditions, the confined and unconfined 
spaces shall be provided with two permanent openings, one near 
the top of the enclosure and one near the bottom; each opening 
shall have a free area of not less than one square inch (6.45cm
2
per 2,000 BTU (.6KW/H) per hour of total input.
LOCATION - ALL MODELS
Select a location near the center of the space to be heated.  Overflow 
heat will circulate through doorways into adjacent rooms. 
For large homes or spread-out floor plans, two or more furnaces are 
recommended.  Do not locate furnace where a door could swing 
over the outer casing, or where circulation could be retarded by 
furniture or cabinets.   
Do not install in a closet, alcove or small hallway where the furnace 
could be isolated by closing doors to the heated space.
When location is selected, check the walls, attic and roof to make 
sure there are no obstructions such as pipes, electric  wiring, etc., 
which would interfere with the installation of the furnace or vent 
pipe.
NOTE:  If Rear Register Kit is to be used, see Rear Register Kit 
instructions for location of hole in rear wall. Register 
outlet must be cut in wall before furnace is installed.
NOTE:  If Optional Blower is to be used, hard wiring must be 
completed for the optional blower prior to installation 
of header plate.
ROUGH-IN INSTRUCTIONS
Provide an opening in the wall 14 1/2" (368mm) wide and 66 
1/8" (168cm) high measured from top of floor plate (See Figure 
2 and Figure 3).  Wall depth is to be 2" x 4" framing with 1/4" 
(6.5mm) to 5/8" (16mm) sheeting. Attach baseplate (not supplied 
with furnace) to header plate with sheet metal screws at each end. 
Attach 4" (102mm) oval, double wall vent pipe to baseplate. Attach 
enough vent pipe so that when installed in wall opening the vent 
pipe will extend above the ceiling plate by at least 6" (152mm). 
Install ceiling spacers according to manufacturer's instructions. 
Insert header plate with attached 4" oval, double wall vent pipe 
into wall opening. Position header plate at height shown in Figure 
2. Locate rear edge of nailing flange at the back of the 2" x 4" stud 
which will center the vent collar in the wall. Locate the angled 
edge of header plate flush with the top of the wall opening. Nail 
header plate to the wall studs. 
NOTE:    Minimum  distance  of  1  1/2"  (38mm)  must  also  be 
maintained from top surface of carpeting, tile, etc.
CLEARANCES