4)  Separate the 2 halves of the wall thimble and 
securely fasten the one with the tabs to the 
outside wall making sure that the tabs are 
on top and bottom. Fasten the other thimble 
half to the inside wall. The thimble halves 
slip inside each other and can be adjusted 
for 2 x 4 or 2 x 6 walls. The liners must slip 
over the collars a minimum of 1-3/8".
5)  Slip  the  assembled  liner  and  termination 
assembly through the thimble making sure 
the  termination  cap  faces  up  (there  are 
markings on the cap that show which way 
is up). This will position the termination cap 
with proper down slope for draining water. 
Fasten the cap to the outer wall with the 4 
supplied screws. 
6)  Pull the centre 4"(100mm) liner and outer 
 
6-7/8"(175mm) liner out enough to slip over 
the fl ue collars of the fi replace.  (You may 
wish to cut the liner shorter to make it more 
workable.)  Do  not  bend  liner  more  than 
90
o
.
7)  Apply Mill Pac over the fi replace inner collar 
and slip the 4"(100mm) liner down over it 
and attach with 3 supplied screws.
8)  Do the same with the 6-7/8"(175mm) liner.
9)  Apply a bead of silicone between the thimble 
and termination and around the outer edge 
of the terminal at the wall in order to keep 
the water out.
IMPORTANT:  Do  not  locate  termination 
hood  where  excessive  snow  or  ice 
buildup may occur. Be sure to check vent 
termination area after snow falls, and clear 
to prevent accidental blockage of venting 
system. When using snow blowers, make 
sure  snow  is  not  directed  towards  vent 
termination area.
N o t e :   To   m a k e 
t h e   i n s t a l l a t i o n 
more  aesthetically 
p l e a s i n g ,   w e 
recommend framing 
out a square to mount 
the terminal to.
Offset Chart
INSTALLATION 
PROCEDURES
for UltraGlow
®
for UltraGlow
for UltraGlow  Direct Vent 
®
®
System (Flex)
1)  Locate the unit in the framing, rough in the 
gas (preferably on the right side of the unit) 
and the electrical (Junction block is on the 
left side) on the left. Locate the centerline of 
the termination and mark wall accordingly. 
Cut a 10"(254mm) hole in the wall (inside 
dimension).
Note:  A  1-1/2"(38mm)  clearance  around 
the liner must be maintained except 
that only a 1" (25mm) clearance is 
needed at the termination end. We 
recommend  framing  a  10"(254mm) 
x  10"(254mm)  (inside  dimensions) 
hole  to  give  structural  rigidity  for 
mounting the termination.
Note:  If installing termination on a siding 
siding 
covered wall,  furring strips must be 
covered wall,  furring strips must be 
used to ensure that the termination 
is not recessed into the siding.
2)  Level the fi replace and fasten it to the framing 
using  nails  or  screws  through  the  nailing 
strips.
3)  Assemble  the  vent  assembly  by  applying 
Mill Pac to the 4"(100mm) inner collar of the 
termination and  slipping the 4"(100mm) liner 
over it at least 1-3/8" (35mm). Fasten with 
the 3 screws (drilling pilot holes will make this 
easier). Apply Mill Pac or high temperature 
silicone to the 6-7/8"(175mm) fl ex pipe and 
slip it over the 6-7/8" outer collar of the vent 
terminal at least 1-3/8"(35mm) and fasten 
with the 3 screws.
NOTE:   Horizontal  sections  must  be 
supported at intervals not exceeding 
3 feet (0.9 meter). (Flame picture and 
performance will be affected by sags 
in the liner).
steep  roof  pitches,  the  vertical  height  must 
be increased.  A poor draft, or down drafting 
can result from high wind conditions near big 
trees or adjoining roof lines, in these cases, 
increasing  the  vent  height  may  solve  the 
problem.
7)  Ensure vent is vertical and secure the base 
of the fl ashing to the roof with roofi ng rails, 
slide storm collar over the pipe section and 
seal with a mastic.
8)  Install the vertical termination cap by twist-
locking it.
Note:  Any closets or storage spaces, which 
the  vent  passes  through  must  be 
enclosed. 
INSTALLATION