Nortel Networks Option 11C Mini Manuale Utente
Chapter 16 — Starting the Option 11C Mini and installing software
Page 211 of 332
Option 11C Mini
Planning and Installation Guide
6
Perform an EDD using Overlay 43.
After the system is loaded, a menu-driven program called the
“Software Installation Program” is automatically called up.
“Software Installation Program” is automatically called up.
—————————— End of Procedure ——————————
Procedure 28
Start-up procedure for a previously installed system
Start-up procedure for a previously installed system
1
Test the power outlet. Make sure that the correct voltage of power is
present before you plug the power cord into the outlet. The source
must match the label on the back of the chassis.
present before you plug the power cord into the outlet. The source
must match the label on the back of the chassis.
2
Connect the power cord from the power connector on the back of the
chassis to an AC power source. See Figure 63. Secure the power
cable with a cable tie.
chassis to an AC power source. See Figure 63. Secure the power
cable with a cable tie.
3
Turn the power switch to “ON”.
4
Observe the TTY or terminal screen.
Messages appear on the TTY or the terminal screen. When the
message “INIXXX” appears, the system is in operation.
message “INIXXX” appears, the system is in operation.
5
If required, set the system time and date using Overlay 2.
6
Perform an EDD using Overlay 43.
—————————— End of Procedure ——————————
Software Installation Program
The Software Installation Program provides a menu-driven method of
selecting from the different options of installing, modifying, or upgrading the
following:
selecting from the different options of installing, modifying, or upgrading the
following:
•
software
•
customer data
•
feature set
•
Incremental Software Management (ISM) parameters