DELL H919N Manuale Utente

Pagina di 73
31
Installation
|
NOTE:
 For Europe, the emergency switch requirements are detailed in Harmonized document HD-384-48 S1,
“Electrical Installation of the Buildings, Part 4: Protection for Safety, Chapter 46: Isolation and Switching.”
REPO Connections
Wire Function
Terminal Wire Size Rating
Suggested Wire Size
REPO
L1
4–0.32 mm
2
 (12–22 AWG)
0.82 mm
2
 (18 AWG)
L2
NOTE:
 The pins must be open to keep the UPS running. If the UPS shuts down because the REPO connector
pins are shorted, restart the UPS by re-opening the REPO connector pins and turning on the UPS manually.
Maximum resistance in the shorted loop is 10 ohm.
NOTE:
 Always test the REPO function before applying your critical load to avoid accidental load loss.
Remove Jumper if
installed
Figure 29. REPO Connector
To install the REPO switch:
1
Verify that the UPS is off and unplugged.
2
Remove the REPO connector from the accessory kit.
NOTE:
 Verify that there is no jumper installed in the REPO connector. If a jumper is installed, remove it before
connecting to the REPO port.
3
Connect the REPO connector to the REPO port labeled “IN” on the UPS rear panel.
4
Optional. 
If you are daisy-chaining the REPO function with another UPS, you can shut down the
entire system using a single switch.
Connect the second REPO connector to the REPO port labeled “OUT.”