Clearances to combustibles
Sidewall Clearances: The clearance from the inside of the firebox 
to perpendicular combustible side wall should not be less than 
6". See Figure 1.
Firebox Side and Back Clearances: The firebox outer casing side 
and back flanges are zero clearance to combustibles.
Top Framing and Finishing: Combustible framing may rest on 
top of standoffs. Combustible finishing materials may extend 
to the top standoff screws on the front edge of the outer wrap. 
See Figure 2.
Ceiling Clearances: The ceiling height should not be less than 42" 
from the top of the hood. See Figure 3.
Mantel Clearances: Vent free firebox models must use the hood 
supplied  with  the  firebox,  or  one  of  the  optional  hood  kits 
available for each model. If a combustible mantel is installed, 
it must meet the clearance requirements detailed below.
Grate Clearance: The minimum clearance between the front legs 
of the grate and front edge of the firebox is 2".
Leave at least 36" clearance from the front of the firebox.
Any vent-free Gas Log Heater must be “For use with approved 
ANSI Z21.11.2 unvented room heater.”
Follow and complete the installation instructions of the gas log set 
and the requirements of this firebox.
Check all fittings for leaks before lighting the gas log set.
In  planning  the  installation  for  the  firebox,  it  is  necessary  to 
determine where the unit is to be installed and whether optional 
accessories are desired. Gas supply piping should also be planned 
at this time.
A gas shut off must be in this line.
45°
6”
3”
MAX.
PERPENDICULAR
SIDE WALL
FRONT FACE (SIDE)
FIREBOX
(TOP VIEW)
COMBUSTIBLE
MATERIALS ALLOWED
IN SHADED AREAS
FIREBOX
STAND OFF
FINISH WITH TRIM KIT OR
NON-COMBUSTIBLE MATERIAL
AS DESIRED.
COMBUSTIBLE
FINISHED WALL
OR MANTEL
2 X 4
HEADER
MANTEL
HOOD
13”
10”
12”
MAX
42”
MIN.
(CEILING TO
TOP OF HOOD)
11 1/2”
MIN.
FIREBOX
FACE
84”
MIN.
(CEILING TO FLOOR)
CEILING
COMBUSTIBLES
ALLOWED
3/8” COMBUSTIBLE
CLEARANCE REQUIRED
FROM TOP EDGE
OF FIREBOX
10”
22”
8”
20”
6 ½”
18”
5”
16”
3 ½”
14”
2”
12 ½”
3/4”
24 ½”
0”
Figure 1
Figure 2
Figure 3