Jet vbs-1610 Guida Utente

Pagina di 28
 
7
6.0  Uncrating and assembly 
1.  Finish uncrating the band saw.  Contact your 
distributor if any damage has occurred during 
shipping. 
2.  Remove any preservative with kerosene or 
diesel oil.  Do not use gasoline, paint thinner, 
or any cellulose-based product, as these will 
damage painted surfaces. 
3.  Remove two socket head cap screws from left 
side of vertical column. Attach shear assembly 
(A, Figure 1) to column by inserting hex cap 
screws. 
4.  Place rip fence onto table and tighten with 
locking knob.  
 
Figure 1 
7.0  Installation 
1.  Remove three (3) nuts and washers holding 
band saw to shipping crate bottom. 
2.  Use the lifting ring to lift band saw into its 
permanent location. For best performance, 
band saw should be bolted to floor after a level 
position has been found. 
3.  Using a square, adjust table 90 degrees to 
blade, both front to back and side to side.  
Loosen the hex cap screws below the table to 
move it and tighten to hold table in place. If 
necessary, adjust the pointers to zero should 
they read different once table is perpendicular 
to blade in both directions. 
4.  To level the machine, place a machinist's level 
on the table and observe in both directions.   
5.  Use metal shims under the appropriate hold 
down screw. Tighten screw and recheck for 
level. 
6.  Adjust with additional shims, as required, until 
table is level when all mounting screws (or 
nuts) are tight. 
8.0  Electrical connections 
  All electrical connections 
must be done by a qualified electrician. All 
adjustments or repairs must be done with 
machine disconnected from power source. 
Failure to comply may cause serious injury.
 
The VBS-1610 Band Saw is rated at 230/460V and 
comes from the factory prewired 230V. 
You may either connect a proper UL-listed plug 
suitable for 230 volt operation, or "hard-wire" the 
machine directly to your electrical panel provided 
there is a disconnect near the machine for the 
operator. 
The band saw must be grounded. A qualified 
electrician can make the proper electrical 
connections and confirm the power on site is 
compatible with the saw. 
Before connecting to power source, make sure 
switch is in off position. 
8.1  Voltage conversion 
To switch to 460V operation: 
1.  Switch the incoming leads in the motor 
junction box (follow wiring diagram on inside 
cover of motor junction box).  
2.  Switch the jumper wires on the circuit board. 
Remove control panel from saw body and 
change the jumper wires according to the list 
in section 19.0, Electrical diagram.  
3.  If a plug is to be used, install a proper UL-
listed plug suitable for 460V operation. 
IMPORTANT: Consult the diagrams in section 19.0 
for any clarification of these changes on 230V to 
460V conversion.  
8.2  Three-phase test run 
After wiring the band saw, you should check that 
the wires have been connected properly. Connect 
machine to power source and turn it on for an 
instant to watch direction of blade movement.  
If blade runs upward instead of downward, 
disconnect machine from power, and switch any 
two of the three leads in the motor junction box 
(see section 19.0, Electrical diagram).