Controlling Production
Defining a Production Day
Figure 2
Production Offset Defined As +1200 (Master/Agent in Same Time Zone)
Negative Offset (Early Start)
If you want your production day to begin at 2045 (8:45 
P
.
M
.), and continue until 2045 the following day, define the 
production day offset as -0315.
The following figure illustrates the calendar and production days with an offset of -0315. Using this production day offset, 
a job scheduled to launch at 2115 on June 12th (production date) launches at 2115 on June 11th (calendar date).
Figure 3
Production Offset Defined As -0315 (Master and Agent in Same Time Zone)